McKay Building Replacement

About the Project

The McKay Building Replacement Project represents the largest capital improvement effort in the history of BYU–Hawaii. Approved by the Board of Trustees, this multi-year initiative will replace several aging campus buildings, including the David O. McKay Classroom Building, the McKay Faculty Building, the Aloha Center, and Flag Circle. The new academic complex is designed to support the university’s mission and future growth.

This transformative project will create modern learning environments, strengthen campus gathering spaces, and enhance student, faculty, and community experiences for decades to come.

Latest Quarterly Update

In June 2026, the underground utility tie-ins are progressing steadily, alongside the successful backfilling and waterproofing of the elevator pit.

Construction across individual structures is moving forward seamlessly. At Building B, Insulated Concrete Form (ICF) installations continue on the East wing while the West wing’s slab-on-grade is now complete.

Meanwhile, concrete pours for the footings remain underway at Building C. Plumbing rough-ins have officially commenced at Building D, where the foundation pad is also nearing completion for the underground sewer settling layout.

View All Project Announcements and Timeline

New McKay Complex Plans

Designed to support learning, collaboration, and community, the new McKay Complex will replace several aging campus buildings. These renderings provide a first look at the updated academic center.

Key Facts & Figures

The new academic complex will include:

  • Five new buildings
  • Total building area: 306,000 sq. ft.
  • Site area: approximately 30 acres
  • Building footprint: 113,000 sq. ft.
  • 30+ modern classrooms and teaching spaces
  • Flexible collaboration and study areas
  • Upgraded utilities and technology infrastructure

Project Information page

Project Timeline

  • 2020–2022: Master Planning
  • 2021–2023: Programming
  • April 2023–July 2024: Design
  • Summer 2023–2024: Construction Documents
  • July 31, 2024: Plans submitted for permitting
    • Permitting expected to take 12–18 months
  • 2025–2030: Construction (estimated 65 months)

Current Phase: Demolition and Site Preparation

View Full Timeline and Project Process

data-content-type="oneOffPage"
overrideBackgroundColorOrImage=#e9b14c overrideTextColor= promoTextAlignment= overrideCardHideSection= overrideCardHideByline= overrideCardHideDescription= overridebuttonBgColor= overrideButtonText= promoTextAlignment=
data-content-type="oneOffPage"
overrideBackgroundColorOrImage=#e9b14c overrideTextColor= promoTextAlignment= overrideCardHideSection= overrideCardHideByline= overrideCardHideDescription= overridebuttonBgColor= overrideButtonText= promoTextAlignment=
overrideBackgroundColorOrImage=#e9b14c overrideTextColor= promoTextAlignment= overrideCardHideSection= overrideCardHideByline= overrideCardHideDescription= overridebuttonBgColor= overrideButtonText=