Recent Construction Updates
McKay Building Replacement
In April 2026, underground utility work was successfully completed, marking a major milestone for the project. Work has now moved into the foundation phase, with deep footings and concrete slabs-on-grade progressing in different stages across Buildings A, B, and D. Crews are actively working on excavation, reinforcing steel, formwork, and concrete placement to keep the project moving forward on schedule.
The front portion of the David O. McKay Building has been removed. The footprint of building A is visible
Aerial view of ongoing site preparation with grading, debris removal, and utility work across the former McKay Building and Flag Circle footprint.
Grading and soil preparation progress where the McKay Foyer once stood, with new contours taking shape around remaining building sections. This area shows continued expansion of groundwork since October as crews prepare the subgrade.
Crews continue grading and compacting the central project area, with soil layers being shaped and leveled for future construction. Compared to October, the work zone shows expanded earthmoving activity and more refined grading contours across the former McKay complex footprint.
A view of the northern edge of the project site where excavation and soil relocation continue. The area previously occupied by walkways and landscaping is now an active grading zone, with compactors and excavators reshaping the ground. Demolition of the old section of the library has begun.
Detailed view of demolition activity along the front wing of the McKay complex. Compared to early October, additional sections of roof and walls have been removed, and debris is being sorted into containers as equipment works along the building line.
Front-facing aerial view of the site showing the cleared Flag Circle area and increased grading and material staging since September. The right side of the McKay Building’s front has been opened up further by demolition, while the left half of the front remains in place.
Early October view showing the McKay Building’s exposed framing after complete roof removal. Debris sorting and staging areas have expanded since September, with work beginning to remove walls and structural components.
Demolition of the north-west wing of the David O. McKay Classroom Building, with site preparation underway across the project area.
Direct overhead view showing the complete removal of Flag Circle and the surrounding roadways and sidewalks. Where the landscaped roundabout and circular lawn once stood, the area is now cleared and graded as crews continue preparing the site.
Forward-facing aerial view of the project site showing the cleared Flag Circle area and the surrounding roadways removed. The front roof section of the McKay Building, which previously faced the circle, has been removed, exposing structural framing.
Mid-September demolition preparation showing the early stages of roof removal on the front portion of the McKay Building. By this point, Flag Circle and the surrounding roads and walkways had already been removed, opening the central area for site preparation.
A mid-September overview showing the site immediately after the removal of Flag Circle and its roads. The front section of the McKay Building remains mostly intact, though early roof removal work is visible as crews prepare for further dismantling.
New Hale Buildings
Significant milestones have been reached at Hale 13, where all irrigation and landscaping work is now officially complete. The project has moved through its final cleaning phases, including a thorough interior deep clean and a full exterior pressure wash. With these finishing touches finalized, the building has been formally turned over to BYU–Hawaii. Meanwhile, site work continues across the broader area, with a primary focus on the retention fields where grass is currently being established and continues to grow.
New TVA Buildings
April 2026, TVA Phase 2b continues to progress at Buildings A5 and A6.
At A5, the courtyard playground is nearing completion, cleaning and pressure washing are ongoing, and mattresses are being placed in units. Landscaping work continues with grass plugs being installed and the backflow system restored. Light poles have also been installed on the west side.
At A6, exterior siding paint is nearing completion on the east side, cabinet installation is complete in east units, and mud, taping, and texture work continue in west units. Stone veneer installation remains ongoing, and Jetcrete flooring has been completed in the level 3 west units.
For Phase 3, elevator pit rebar at Building B5 has been inspected, and the first concrete pour has been completed. Crews are also continuing underground mechanical, electrical, and plumbing (MEP) rough-in work that will support future building systems later in construction.