Skip to main content

Recent Construction Updates

McKay Building Replacement

In April 2026, underground utility work was successfully completed, marking a major milestone for the project. Work has now moved into the foundation phase, with deep footings and concrete slabs-on-grade progressing in different stages across Buildings A, B, and D. Crews are actively working on excavation, reinforcing steel, formwork, and concrete placement to keep the project moving forward on schedule.

New Hale Buildings

Significant milestones have been reached at Hale 13, where all irrigation and landscaping work is now officially complete. The project has moved through its final cleaning phases, including a thorough interior deep clean and a full exterior pressure wash. With these finishing touches finalized, the building has been formally turned over to BYU–Hawaii. Meanwhile, site work continues across the broader area, with a primary focus on the retention fields where grass is currently being established and continues to grow.

New TVA Buildings

April 2026, TVA Phase 2b continues to progress at Buildings A5 and A6.

At A5, the courtyard playground is nearing completion, cleaning and pressure washing are ongoing, and mattresses are being placed in units. Landscaping work continues with grass plugs being installed and the backflow system restored. Light poles have also been installed on the west side.

At A6, exterior siding paint is nearing completion on the east side, cabinet installation is complete in east units, and mud, taping, and texture work continue in west units. Stone veneer installation remains ongoing, and Jetcrete flooring has been completed in the level 3 west units.

For Phase 3, elevator pit rebar at Building B5 has been inspected, and the first concrete pour has been completed. Crews are also continuing underground mechanical, electrical, and plumbing (MEP) rough-in work that will support future building systems later in construction.