TVA Projects Announcements and Timeline

January to March 2026 TVA Construction Gallery

September to December 2025 TVA Construction Gallery

Announcements and Updates

  • TVA Phase 2

    • A5
      • Punchlist work is complete
      • Playground work is complete
      • Grass continues to grow
      • Light pole work for A5 is complete
      • Building has been turned over to the campus and is now being used
    • A6
      • Painting for all units is complete
      • Cabinets have been installed in all units
      • Stone veneer work continues around the building
      • Benches are complete in the courtyard
      • Handrails will be installed next week
      • Sink fixtures are being installed
      • Millwork is ongoing in each unit

    B5 (Phase 3)

    • Rebar has been placed and tied on the East side
    • Underground plumbing work is complete
    • First concrete foundation pour will take place this week
  • TVA Phase 2

    • A5
      • Punch list and clean-up work is ongoing in each unit
      • Bike racks have been installed on the East side walk area
      • The playground is complete, and turf installation is complete
      • Trees continue to grow and grass plugs have been planted and are taking root
      • Electrical work for the light poles continues on the West side of A5
    • A6
      • Painting on the exterior walls is complete
      • Cabinets have been installed on all the East Units and second-level West units
      • Painting is ongoing in the North West and West units of level 1 and 3
      • Stone veneer work continues around the building
      • Concrete has been poured for the benches in the courtyard
      • Baseboard installation has started in the East units

    B5 (Phase 3)

    • Building pad work is complete
    • Concrete for the walls and base of the elevator pit has been poured
    • Underground plumbing work is ongoing
  • TVA Phase 2

    • A5
      • Punchlist and clean-up work is ongoing in each unit
      • The sidewalk and bike rack that tie into Naniloa Loop have been poured
      • Courtyard sidewalks have been poured, and playground turf has been installed
      • Elevator inspection is completed and has passed state inspection
      • Topsoil has been placed and trees and small plants have been planted
    • A6
      • Exterior siding panels are being painted on the West side
      • Cabinets are being installed in the East units of each floor
      • Drywall work is complete on the West units of each floor; texture paint is not ongoing
      • Insulation continues to be installed on the North Units of each floor
      • Stone veneer continues on the outer walls of the building

    Phase 3

    • Building pad work has begun and is ongoing
    • Excavation for the elevator pit is complete
    • Underground Mechanical, Electrical and Plumbing (MEP) rough-in has started
  • TVA Phase 2

    • A5
      • Punchlist work has started and is ongoing through each unit
      • Fire Alarm work in the building nears completion
      • Concrete for the sidewalk and bike racks that connect to Naniloa will be poured this week
      • Courtyard sidewalks have been poured, turf to be installed this week and next week
      • The Elevator is complete and will be inspected by the state in April
      • Top soil for landscaping is being placed around the building
    • A6
      • Exterior siding panels are being painted around the building
      • Flooring and painting are complete on the East units of floors 2 and 3
      • Drywall and painting are ongoing in the East units on the first floor
      • Insulation continues to be installed on the West units of each floor
      • Stone veneer work is progressing around the outside and inside walls of the building

    Phase 3

    • Building Permits have been received
    • Building pad work will begin next week
  • TVA Phase 2

    • A5
      • All of the cabinets and countertops have been installed for each unit
      • Appliance installation continues throughout the building
      • Sink installation is ongoing for the west units
      • Concrete for the courtyard benches has been poured
      • Exterior door locks are being installed for the exterior doors
    • A6
      • Roofing underlayment and shingles have all been laid
      • Plumbers have completed roof vent work
      • Green vapor barrier has been installed on the inside walls of each floor
      • Concrete walkways for level 2 have been poured; level 3 will be poured this week
      • Windows continue to be installed around the North and West sides of the building

    Phase 3

    • The permitting process continues
  • TVA Phase 2

    • A5
      • All the exterior walls have been painted
      • Interior walls have been framed on all levels
      • Plumbing and electrical fixtures installation nears completion
      • Drywall work is complete in all units
      • Cabinets and countertops are going to be installed in all units before the 24th of December
      • Flooring has been installed in all units
    • A6
      • All ICF (Insulated Concrete Forms) have been placed and grouted
      • Trusses and sheathing have been placed for the East and North sides of the building
      • Plumbing and fire sprinkler rough-in is in progress on the third level
      • Electricians are working on in-wall and fire alarm rough-in on the third floor

    Phase 3

    • Abatement and demolition of buildings J, K, L, and M are complete, and all debris has been hauled off the site
    • Electrical and sewer tie-in for phase 3 is ongoing
  • TVA Phase 2

    • A4

      • Appliances have been installed in all the units.
      • Interior finishes and fixtures are complete.
      • Furniture has been delivered and placed in each unit.
      • The last of the underground utilities work is nearly complete.
    • A5

      • ICF walls have been completed up to the third level. ICF form installation continues on the third level.
      • Third-level floor system framing and sheathing in progress.
      • Interior walls are being framed on the second level.
      • Plumbing rough-in complete on first level.
    • A6

      • Underground plumbing has been installed on the east side.
      • Concrete forms are currently being built, and preparation for pouring the mat slab is in progress.
      • West side underground plumbing work is in progress.

    Phase 3 Preparation:

    • The road near the site remains closed.
    • Site grading is in progress where Building H is located.