TVA Projects Announcements and Timeline
January to March 2026 TVA Construction Gallery
1
of
17
September to December 2025 TVA Construction Gallery
1
of
23
Announcements and Updates
-
Toggle ItemJune 2026
TVA Phase 2
- A5
- Punchlist work is complete
- Playground work is complete
- Grass continues to grow
- Light pole work for A5 is complete
- Building has been turned over to the campus and is now being used
- A6
- Painting for all units is complete
- Cabinets have been installed in all units
- Stone veneer work continues around the building
- Benches are complete in the courtyard
- Handrails will be installed next week
- Sink fixtures are being installed
- Millwork is ongoing in each unit
B5 (Phase 3)
- Rebar has been placed and tied on the East side
- Underground plumbing work is complete
- First concrete foundation pour will take place this week
- A5
-
Toggle ItemMay 2026
TVA Phase 2
- A5
- Punch list and clean-up work is ongoing in each unit
- Bike racks have been installed on the East side walk area
- The playground is complete, and turf installation is complete
- Trees continue to grow and grass plugs have been planted and are taking root
- Electrical work for the light poles continues on the West side of A5
- A6
- Painting on the exterior walls is complete
- Cabinets have been installed on all the East Units and second-level West units
- Painting is ongoing in the North West and West units of level 1 and 3
- Stone veneer work continues around the building
- Concrete has been poured for the benches in the courtyard
- Baseboard installation has started in the East units
B5 (Phase 3)
- Building pad work is complete
- Concrete for the walls and base of the elevator pit has been poured
- Underground plumbing work is ongoing
- A5
-
Toggle ItemApril 2026
TVA Phase 2
- A5
- Punchlist and clean-up work is ongoing in each unit
- The sidewalk and bike rack that tie into Naniloa Loop have been poured
- Courtyard sidewalks have been poured, and playground turf has been installed
- Elevator inspection is completed and has passed state inspection
- Topsoil has been placed and trees and small plants have been planted
- A6
- Exterior siding panels are being painted on the West side
- Cabinets are being installed in the East units of each floor
- Drywall work is complete on the West units of each floor; texture paint is not ongoing
- Insulation continues to be installed on the North Units of each floor
- Stone veneer continues on the outer walls of the building
Phase 3
- Building pad work has begun and is ongoing
- Excavation for the elevator pit is complete
- Underground Mechanical, Electrical and Plumbing (MEP) rough-in has started
- A5
-
Toggle ItemMarch 2026
TVA Phase 2
- A5
- Punchlist work has started and is ongoing through each unit
- Fire Alarm work in the building nears completion
- Concrete for the sidewalk and bike racks that connect to Naniloa will be poured this week
- Courtyard sidewalks have been poured, turf to be installed this week and next week
- The Elevator is complete and will be inspected by the state in April
- Top soil for landscaping is being placed around the building
- A6
- Exterior siding panels are being painted around the building
- Flooring and painting are complete on the East units of floors 2 and 3
- Drywall and painting are ongoing in the East units on the first floor
- Insulation continues to be installed on the West units of each floor
- Stone veneer work is progressing around the outside and inside walls of the building
Phase 3
- Building Permits have been received
- Building pad work will begin next week
- A5
-
Toggle ItemJanuary 2026
TVA Phase 2
- A5
- All of the cabinets and countertops have been installed for each unit
- Appliance installation continues throughout the building
- Sink installation is ongoing for the west units
- Concrete for the courtyard benches has been poured
- Exterior door locks are being installed for the exterior doors
- A6
- Roofing underlayment and shingles have all been laid
- Plumbers have completed roof vent work
- Green vapor barrier has been installed on the inside walls of each floor
- Concrete walkways for level 2 have been poured; level 3 will be poured this week
- Windows continue to be installed around the North and West sides of the building
Phase 3
- The permitting process continues
- A5
-
Toggle ItemOctober 2025
TVA Phase 2
- A5
- All the exterior walls have been painted
- Interior walls have been framed on all levels
- Plumbing and electrical fixtures installation nears completion
- Drywall work is complete in all units
- Cabinets and countertops are going to be installed in all units before the 24th of December
- Flooring has been installed in all units
- A6
- All ICF (Insulated Concrete Forms) have been placed and grouted
- Trusses and sheathing have been placed for the East and North sides of the building
- Plumbing and fire sprinkler rough-in is in progress on the third level
- Electricians are working on in-wall and fire alarm rough-in on the third floor
Phase 3
- Abatement and demolition of buildings J, K, L, and M are complete, and all debris has been hauled off the site
- Electrical and sewer tie-in for phase 3 is ongoing
- A5
-
Toggle ItemApril 2025
TVA Phase 2
A4
- Appliances have been installed in all the units.
- Interior finishes and fixtures are complete.
- Furniture has been delivered and placed in each unit.
- The last of the underground utilities work is nearly complete.
A5
- ICF walls have been completed up to the third level. ICF form installation continues on the third level.
- Third-level floor system framing and sheathing in progress.
- Interior walls are being framed on the second level.
- Plumbing rough-in complete on first level.
A6
- Underground plumbing has been installed on the east side.
- Concrete forms are currently being built, and preparation for pouring the mat slab is in progress.
- West side underground plumbing work is in progress.
Phase 3 Preparation:
- The road near the site remains closed.
- Site grading is in progress where Building H is located.