The newest edition to the ongoing construction is the Propane Farm Project. This project will consist of installing two 12,000-gallon LPG tanks near the CAC building. These propane tanks will be able to supply gas to all of campus. The purpose of this project is to add to the reduction of the traditional use of power, which will allow BYUH to become more self-sufficient and independent.
1
of
3
Timeline and Updates of the Project
Completion Date
September 2023
Recent Updates
July 2023
Excavation for the courtyard is planned for the end of the month to facilitate the gas line installation.
August 2023
Excavation work has started for the courtyard area in preparation for Hawaii Gas to install their gas line. September 2023
Work for this project has been successfully completed.