New TVA Buildings

Construction Gallery

April 2026, TVA Phase 2b continues to progress at Buildings A5 and A6.

At A5, the courtyard playground is nearing completion, cleaning and pressure washing are ongoing, and mattresses are being placed in units. Landscaping work continues with grass plugs being installed and the backflow system restored. Light poles have also been installed on the west side.

At A6, exterior siding paint is nearing completion on the east side, cabinet installation is complete in east units, and mud, taping, and texture work continue in west units. Stone veneer installation remains ongoing, and Jetcrete flooring has been completed in the level 3 west units.

For Phase 3, elevator pit rebar at Building B5 has been inspected, and the first concrete pour has been completed. Crews are also continuing underground mechanical, electrical, and plumbing (MEP) rough-in work that will support future building systems later in construction.

About This Project


Additional Temple View Apartments are under construction. Temple View Apartment Buildings A3 and B3 are another two of the three structures for the second phase of the New Temple View Apartment Project. These two buildings have the same structure as in the new TVA Building A1, with a little difference in the exterior. Like the new TVA Building A1, TVA A3 and B3 will be constructed with insulated concrete forms (ICF) that have no wood to overcome many of the challenges of the existing construction. They are hurricane-resistant, mold-resistant, and insect-resistant and have high insulation value. Each unit will have the following:

  1. 9’-0” ceilings.
  2. Windows are located to increase airflow inside the unit to improve passive cooling.
  3. High-efficiency hot water system.
  4. Each unit has individual WIFI.
  5. Each unit has its own washer and dryer.
  6. New LED light fixtures.
  7. New hardwood cabinets.
  8. New quartz countertops.
  9. New luxury vinyl Tile flooring.
  10. New high-efficiency appliances.
  11. New furnishings.

Timeline and Updates of the Project

Completion Date

TVA A3-April 2024

TVA B3-August 2024

TVA B4-September 2024

TVA A4-February 2026

Recent Updates

April 2025

TVA Phase 2

  • A4:
    • Appliances have been installed in all the units.
    • Interior finishes and fixtures are complete.
    • Furniture has been delivered and placed in each unit.
    • The last of the underground utilities work is nearly complete.
  • A5:
    • ICF walls have been completed up to the third level. ICF form installation continues on the third level.
    • Third-level floor system framing and sheathing in progress.
    • Interior walls are being framed on the second level.
    • Plumbing rough-in complete on first level.
  • A6
    • Underground plumbing has been installed on the east side.
    • Concrete forms are currently being built, and preparation for the mat slab to be poured is in progress.
    • West side underground plumbing work in progress.

Phase 3 Preparation:

  • The road near the site remains closed.
  • Site grading is in progress where Building H is located.