NEW TVA BUILDINGS
1 of 3
Image of New Temple View Apartment #1
2 of 3
TVA housing Building.PNG
3 of 3
TVA housing building2.PNG
Planning, Design & Construction Department
1
of
3
1 of 3
Image of New Temple View Apartment #1
2 of 3
TVA housing Building.PNG
3 of 3
TVA housing building2.PNG
Planning, Design & Construction Department
1
of
3
About This Project
Additional Temple View Apartments are under construction. Temple View Apartment Buildings A3 and B3 are another two of the three structures for the second phase of the New Temple View Apartment Project. These two buildings have the same structure as in the new TVA Building A1, with a little difference in the exterior. Like the new TVA Building A1, TVA A3 and B3 will be constructed with insulated concrete forms (ICF) that have no wood to overcome many of the challenges of the existing construction. They are hurricane-resistant, mold-resistant, and insect-resistant and have high insulation value. Each unit will have the following:
- 9’-0” ceilings.
- Windows are located to increase airflow inside the unit to improve passive cooling.
- High-efficiency hot water system.
- Each unit has individual WIFI.
- Each unit has its own washer and dryer.
- New LED light fixtures.
- New hardwood cabinets.
- New quartz countertops.
- New luxury vinyl Tile flooring.
- New high-efficiency appliances.
- New furnishings.
1 of 4
Building A3-12.08.2023.png
Planning, Design & Construction
2 of 4
Building B3-12.08.2023.png
Planning, Design & Construction
3 of 4
Building B4-12.08.2023.png
Planning, Design & Construction
4 of 4
TVA Phase 2-12.08.2023.png
Planning, Design & Construction
1
of
4
1 of 4
Building A3-12.08.2023.png
Planning, Design & Construction
2 of 4
Building B3-12.08.2023.png
Planning, Design & Construction
3 of 4
Building B4-12.08.2023.png
Planning, Design & Construction
4 of 4
TVA Phase 2-12.08.2023.png
Planning, Design & Construction
1
of
4
Timeline and Updates of the Project
Completion Date
TVA A3-April 2024
TVA B3-August 2024
TVA B4-September 2024
TVA A4-February 2026
Recent Updates
December 2023
- Building A3: Electricians are putting the finishing touches on all rooms, electrical vehicle charging stations have been poured in place, and a final walk-through of the building is scheduled for mid-January.
- Building B3: Significant progress has been made, including painting the top two floors. Elevator installation is ongoing.
- Building B4: All siding has been installed, and masons are completing work on the final columns. The dumpster pad enclosure has been installed.
- Building A4: Extensive plumbing installation is commencing.
Construction Gallery
1 of 29
TVA Phase 2.PNG
Planning, Design & Construction
2 of 29
TVA 11.11 Phase 2.PNG
Planning, Design & Construction Department
3 of 29
TVA 11.11 Phase 2.2 B3 Bldg Pad.PNG
Planning, Design & Construction
4 of 29
TVA 11.11 Phase 2.3 A3 Under Mat Slab utilities.PNG
Planning, Design & Construction
5 of 29
TVA 11.12 Phase 2.1.PNG
Planning, Design & Construction Department
6 of 29
Demolition of TVA BLDG. G.PNG
Planning, Design & Construction
7 of 29
A3 TVA.PNG
Planning, Design & Construction
8 of 29
Mat Slab-Concrete-TVA B3.PNG
Planning, Design & Construction
9 of 29
February 3, 2023- B3 and B4.PNG
Planning, Design & Construction Department
10 of 29
A3-February 3, 2023.PNG
Planning, Design & Construction Department
11 of 29
Feb 15- TVA PHASE 2.PNG
Planning, Design & Construction Department
12 of 29
Feb 15-TVA B4.PNG
Planning, Design & Construction Department
13 of 29
Feb 15-B3.PNG
Planning, Design & Construction Department
14 of 29
Feb 15-TVA A3.PNG
Planning, Design & Construction Department
15 of 29
TVA A3-March 14, 2023.PNG
Planning, Design & Construction
16 of 29
B4.png
Planning, Design & Construction
17 of 29
B4-May 2023.png
Planning, Design & Construction
18 of 29
May 2, 2023-A3 Back Exterior.png
Planning, Design & Construction
19 of 29
Building B4.2023.05.30.png
Planning, Design & Construction
20 of 29
Building B3 2023.05.30.png
Planning, Design & Construction
21 of 29
Building A3-2023.05.30.png
Planning, Design & Construction
22 of 29
A3 back side 6-30-23.png
Planning, Design & Construction Department
23 of 29
TVA A3 June 30, 2023.png
Planning, Design & Construction Updates
24 of 29
TVA Phase 2 June 30, 2023.png
Planning, Design & Construction Department
25 of 29
Sept 15, 2023-B3.png
Planning, Design & Construction
26 of 29
A3. 2023.09.15.png
Planning, Design & Construction
27 of 29
B4-Sep 15, 2023.png
Planning, Design & Construction
28 of 29
Sept 15, 2023-A3.png
Planning, Design & Construction
29 of 29
A3-Sept 15, 2023.png
Planning, Design & Construction
1
of
29
1 of 29
TVA Phase 2.PNG
Planning, Design & Construction
2 of 29
TVA 11.11 Phase 2.PNG
Planning, Design & Construction Department
3 of 29
TVA 11.11 Phase 2.2 B3 Bldg Pad.PNG
Planning, Design & Construction
4 of 29
TVA 11.11 Phase 2.3 A3 Under Mat Slab utilities.PNG
Planning, Design & Construction
5 of 29
TVA 11.12 Phase 2.1.PNG
Planning, Design & Construction Department
6 of 29
Demolition of TVA BLDG. G.PNG
Planning, Design & Construction
7 of 29
A3 TVA.PNG
Planning, Design & Construction
8 of 29
Mat Slab-Concrete-TVA B3.PNG
Planning, Design & Construction
9 of 29
February 3, 2023- B3 and B4.PNG
Planning, Design & Construction Department
10 of 29
A3-February 3, 2023.PNG
Planning, Design & Construction Department
11 of 29
Feb 15- TVA PHASE 2.PNG
Planning, Design & Construction Department
12 of 29
Feb 15-TVA B4.PNG
Planning, Design & Construction Department
13 of 29
Feb 15-B3.PNG
Planning, Design & Construction Department
14 of 29
Feb 15-TVA A3.PNG
Planning, Design & Construction Department
15 of 29
TVA A3-March 14, 2023.PNG
Planning, Design & Construction
16 of 29
B4.png
Planning, Design & Construction
17 of 29
B4-May 2023.png
Planning, Design & Construction
18 of 29
May 2, 2023-A3 Back Exterior.png
Planning, Design & Construction
19 of 29
Building B4.2023.05.30.png
Planning, Design & Construction
20 of 29
Building B3 2023.05.30.png
Planning, Design & Construction
21 of 29
Building A3-2023.05.30.png
Planning, Design & Construction
22 of 29
A3 back side 6-30-23.png
Planning, Design & Construction Department
23 of 29
TVA A3 June 30, 2023.png
Planning, Design & Construction Updates
24 of 29
TVA Phase 2 June 30, 2023.png
Planning, Design & Construction Department
25 of 29
Sept 15, 2023-B3.png
Planning, Design & Construction
26 of 29
A3. 2023.09.15.png
Planning, Design & Construction
27 of 29
B4-Sep 15, 2023.png
Planning, Design & Construction
28 of 29
Sept 15, 2023-A3.png
Planning, Design & Construction
29 of 29
A3-Sept 15, 2023.png
Planning, Design & Construction
1
of
29