Skip to main content

New TVA Buildings

About This Project


Additional Temple View Apartments are under construction. Temple View Apartment Buildings A3 and B3 are another two of the three structures for the second phase of the New Temple View Apartment Project. These two buildings have the same structure as in the new TVA Building A1, with a little difference in the exterior. Like the new TVA Building A1, TVA A3 and B3 will be constructed with insulated concrete forms (ICF) that have no wood to overcome many of the challenges of the existing construction. They are hurricane-resistant, mold-resistant, and insect-resistant and have high insulation value. Each unit will have the following:

  1. 9’-0” ceilings.
  2. Windows are located to increase airflow inside the unit to improve passive cooling.
  3. High-efficiency hot water system.
  4. Each unit has individual WIFI.
  5. New quartz countertops.
  6. Each unit has its own washer and dryer.
  7. New LED light fixtures.
  8. New hardwood cabinets.
  9. New luxury vinyl Tile flooring.
  10. New high-efficiency appliances.
  11. New furnishings.

Timeline and Updates of the Project

Completion Date

Estimated Completion Date

Open Date

TVA–A3April 2024March 27, 2024
TVA–A4February 2026Aug. 25, 2025
TVA–B3August 2024May 2, 2024
TVA–B4September 2024June 20, 2024

View TVA Projects Announcements and Timeline

Latest Quarterly Update

In June 2026, TVA Phase 2 continues to progress at Buildings A5 and A6.

At A5, punch list work, light pole installation, and the playground have been completed. Turf establishment continues. The building has been turned over to the campus and is now occupied.

At A6, painting is complete, and cabinets have been installed in all units. Stone veneer installation continues around the building, while courtyard benches have been completed. Sink fixtures are currently being installed, and millwork continues in each unit. Handrail installation will begin soon.

For Phase 3, at B5, underground plumbing is complete. Rebar placement and tie installation have been completed on the east side, and the first concrete foundation pour will take place soon.

Rendering of the TVA Building Project