Work on TVA Phase 2 is progressing rapidly. At Building A5, the exterior is fully painted and interior framing is complete. With drywall and flooring already installed, crews are finalizing plumbing and electrical fixtures. Cabinet and countertop installations are on track to be completed in all units by Dec. 24. At Building A6, all insulated concrete forms are grouted and roof trusses are in place on the east and north sides. Third-level rough-ins for plumbing, fire sprinklers, and electrical systems are currently underway.
In Phase 3, the site has been cleared following the abatement and demolition of Buildings J, K, L, and M. All debris has been removed, and teams are now focused on completing the essential electrical and sewer tie-ins for the next stage of construction.
1 of 55
Feb 2025-A4.jpg
A4–February 2025
Planning, Design & Construction Department
2 of 55
A5-Feb 2025.jpg
A5 Building–February 2025
Planning, Design & Construction Department
3 of 55
A4-Feb 2025.jpg
A4 Building–February 2025
Planning, Design & Construction Department
4 of 55
TVA Phase 2 Overview-Feb 2025.jpg
TVA Phase 2–February 2025
Planning, Design & Construction Department
5 of 55
A5-Dec 2024.JPG
December 2024–TVA A5
Planning, Design & Construction Department
6 of 55
A4-Dec. 2024.JPG
December 2024–TVA A4
Planning, Design & Construction Department
7 of 55
Dec. 2024-A4 Bedroom.jpg
December 2024–A4
Planning, Design & Construction Department
8 of 55
Dec. 2024-A4.jpg
December 2024–A4
Planning, Design & Construction Department
9 of 55
Dec. 2024-TVA Phase 2.jpg
December 2024–TVA Phase 2
Planning, Design & Construction Department
10 of 55
A4-Sep 2024.png
September 13, 2024–TVA A4
11 of 55
Sep.13.2024-A4 (1).jpg
September 13, 2024- TVA A4
12 of 55
A3-2024.png
July 3, 2024–Completed Construction TVA A3 Building
Planning, Design & Construction Department
13 of 55
2024 TVA.png
July 3, 2024–New TVA Housing Project Phase 2 Construction
Planning, Design & Construction Department
14 of 55
B4 2024.png
July 3, 2024–TVA B4 Housing Construction
Planning, Design & Construction Department
15 of 55
B3 & B4 backyard.png
May 15, 2024- TVA B4 & B3 Landscaping
Planning, Design & Construction Department
16 of 55
TVA Building B3.JPG
May 20, 2024-TVA B3 Completion
Planning, Design & Construction Department
17 of 55
TVA Building B4.JPG
May 20, 2024- Landscaping and Interior Development.
Planning, Design & Construction Department
18 of 55
TVA Building A4.JPG
May 20, 2024- Progressing Construction of ICF Walls on the First Floor, Steel Framework for Second Level Underway
Planning, Design & Construction Department
19 of 55
B4-April 26, 2024.png
April 26, 2024- B4 Building Exterior Nearing Completion
Planning, Design & Construction Department
20 of 55
b3-April 24, 2026.png
April 26, 2024-TVA B3 – Final Touches and Preparations Underway
Planning, Design & Construction Department
21 of 55
2024-A3-March.png
April 26, 2024-Temple View Apartment A3 Completion
Planning, Design & Construction Department
22 of 55
Building B3-12.08.2023.png
December 8, 2023 - Construction Progress Update of B3 Building
Planning, Design & Construction
23 of 55
Building A3-12.08.2023.png
December 8, 2023-Building A3 Construction Completion
Planning, Design & Construction
24 of 55
Building B4-12.08.2023.png
December 29, 2023-Construction Progress:Building B4 Facade
Planning, Design & Construction
25 of 55
B4-Sep 15, 2023.png
September 15, 2023 - TVA Phase 2 Building B4 Construction
Planning, Design & Construction
26 of 55
A3. 2023.09.15.png
September 15, 2023 - TVA Phase 2 Building A3 construction
Planning, Design & Construction
27 of 55
Sept 15, 2023-B3.png
September 5, 2023- TVA Phase 2 Building B3 Construction
Planning, Design & Construction
28 of 55
A3-Sept 15, 2023.png
September 15, 2023- Dining Area/TVA A3
Planning, Design & Construction
29 of 55
Sept 15, 2023-A3.png
September 5, 2023 - TVA A3 (Dining Area)
Planning, Design & Construction
30 of 55
A3. 2023.09.15.png
September 15, 2023 - TVA Phase 2 Building A3 construction
Planning, Design & Construction
31 of 55
Sept 15, 2023-B3.png
September 5, 2023- TVA Phase 2 Building B3 Construction
Planning, Design & Construction
32 of 55
TVA Phase 2 June 30, 2023.png
June 30, 2023 – TVA Phase 2 Construction site
Planning, Design & Construction Department
33 of 55
TVA A3 June 30, 2023.png
June 30-2023 – A3 front windows and door installation
Planning, Design & Construction Updates
34 of 55
A3 back side 6-30-23.png
June 30, 2023 – A3 Back Side Completion
Planning, Design & Construction Department
35 of 55
Building A3-2023.05.30.png
May 30, 2023 – Elevator shaft completed
Planning, Design & Construction
36 of 55
Building B3 2023.05.30.png
May 30, 2023- Installation of insulated concrete form walls for building B3
Planning, Design & Construction
37 of 55
Building B4.2023.05.30.png
May 30, 2023- Progress Photo of Building B4
Planning, Design & Construction
38 of 55
May 2, 2023-A3 Back Exterior.png
May 2, 2023- A3 Building Back Exterior
Planning, Design & Construction
39 of 55
B4-May 2023.png
May 2, 2023- B4 Building Mat Slab on Grade
Planning, Design & Construction
40 of 55
B4.png
March 7, 2023- Building B3 & B4
Planning, Design & Construction
41 of 55
TVA A3-March 14, 2023.PNG
March 7, 2023-Building A3
Planning, Design & Construction
42 of 55
Feb 15-TVA A3.PNG
February 15, 2023- (TVA A3 Update)
Planning, Design & Construction Department
43 of 55
Feb 15-B3.PNG
February 15, 2023- (TVA B3 Update)
Planning, Design & Construction Department
44 of 55
Feb 15-TVA B4.PNG
February 15, 2023- (TVA B4 Update)
Planning, Design & Construction Department
45 of 55
Feb 15- TVA PHASE 2.PNG
February 15, 2023- TVA Phase 2 Project Side View
Planning, Design & Construction Department
46 of 55
A3-February 3, 2023.PNG
January 27, 2023-Building B4
Planning, Design & Construction Department
47 of 55
February 3, 2023- B3 and B4.PNG
January 27, 2023- Building A3
Planning, Design & Construction Department
48 of 55
Mat Slab-Concrete-TVA B3.PNG
January 6, 2023- Building B3 Foot Plan
Planning, Design & Construction
49 of 55
A3 TVA.PNG
January 6, 2023- A3 Building Pad
Planning, Design & Construction
50 of 55
Demolition of TVA BLDG. G.PNG
January 6, 2023-Building G Demolition Construction Site
Planning, Design & Construction
51 of 55
TVA 11.12 Phase 2.1.PNG
November 11, 2022- TVA Phase 2 Update
Planning, Design & Construction Department
52 of 55
TVA 11.11 Phase 2.3 A3 Under Mat Slab utilities.PNG
November 11, 2022- TVA Phase 2 Update
Planning, Design & Construction
53 of 55
TVA 11.11 Phase 2.2 B3 Bldg Pad.PNG
November 11, 2022- TVA Phase 2 Update
Planning, Design & Construction
54 of 55
TVA 11.11 Phase 2.PNG
November 11, 2022- TVA Phase 2 Update
Planning, Design & Construction Department
55 of 55
TVA Phase 2.PNG
January 6, 2023- (TVA Phase 2 Project Construction Site)
Planning, Design & Construction