Skip to main content

NEW TVA BUILDINGS

About This Project


Additional Temple View Apartments are under construction. Temple View Apartment Buildings A3 and B3 are another two of the three structures for the second phase of the New Temple View Apartment Project. These two buildings have the same structure as in the new TVA Building A1, with a little difference in the exterior. Like the new TVA Building A1, TVA A3 and B3 will be constructed with insulated concrete forms (ICF) that have no wood to overcome many of the challenges of the existing construction. They are hurricane-resistant, mold-resistant, and insect-resistant and have high insulation value. Each unit will have the following:

  1. 9’-0” ceilings.
  2. Windows are located to increase airflow inside the unit to improve passive cooling.
  3. High-efficiency hot water system.
  4. Each unit has individual WIFI.
  5. Each unit has its own washer and dryer.
  6. New LED light fixtures.
  7. New hardwood cabinets.
  8. New quartz countertops.
  9. New luxury vinyl Tile flooring.
  10. New high-efficiency appliances.
  11. New furnishings.

Timeline and Updates of the Project

Completion Date

TVA A3-April 2024
TVA B3-August 2024
TVA B4-September 2024
TVA A4-February 2026

Recent Updates

December 2023

  • Building A3: Electricians are putting the finishing touches on all rooms, electrical vehicle charging stations have been poured in place, and a final walk-through of the building is scheduled for mid-January.
  • Building B3: Significant progress has been made, including painting the top two floors. Elevator installation is ongoing.
  • Building B4: All siding has been installed, and masons are completing work on the final columns. The dumpster pad enclosure has been installed.
  • Building A4: Extensive plumbing installation is commencing.

Construction Gallery