Significant milestones have been reached at Hale 13, where all irrigation and landscaping work is now officially complete. The project has moved through its final cleaning phases, including a thorough interior deep clean and a full exterior pressure wash. With these finishing touches finalized, the building has been formally turned over to BYU–Hawaii. Meanwhile, site work continues across the broader area, with a primary focus on the retention fields where grass is currently being established and continues to grow.
1 of 93
Project Overview-New Hales.jpg
February 2025–Project Overview of New Hales
Planning, Design & Construction Department
2 of 93
Hale 13 Front-Feb 2025.jpg
February 2025–Hale 13
Planning, Design & Construction Department
3 of 93
Hale 12-Feb 2025.jpg
February 2025–Hale 12
Planning, Design & Construction Department
4 of 93
Hale 12 Backside-Feb 2025.jpg
February 2025–Hale 12
Planning, Design & Construction Department
5 of 93
Hale 13-Feb 2025.jpg
February 2025–Hale 13
Planning, Design & Construction Department
6 of 93
Hale 12 & Hale 13-Feb 2025.jpg
February 2025–Campus New Hales
Planning, Design & Construction Department
7 of 93
Dec. 2024-Hale 13.JPG
December 2024–Hale 13
Planning, Design & Construction Department
8 of 93
Surf & Bike racks 2024.jpg
November 2024–Hale 11
Planning, Design & Construction Department
9 of 93
Hale 12-Dec 2024.JPG
December 2024–Hale 12
Planning, Design & Construction Department
10 of 93
Dec. 2024-Hale 12.JPG
December 2024–Hale 12
Planning, Design & Construction Department
11 of 93
Hale 13-Novmeber 2024.jpg
November 2024–Hale 13
Planning, Design & Construction Department
12 of 93
Hale 12-Nov. 2024.jpg
November 2024–Hale 12
Planning, Design & Construction Department
13 of 93
Nov. 2024-Hale 11-Interior.jpg
Hale 11
Planning, Design & Construction Department
14 of 93
Hale 13-Aerial View.jpg
September 12, 2024-Hale 13
15 of 93
Nov. 2024, Hale 11.jpg
November 2024–Hale 11
Planning, Design & Construction Department
16 of 93
Hale 13 Living room.png
September 23, 2024–Living Area Space
17 of 93
Hale 13 common area.png
September 23, 2024–Common Room
18 of 93
Hale 12-Sep 2024.jpg
September 23, 2024–Hale 12
19 of 93
Hale 11-sep 2024.jpg
September 23, 2024-Hale 11
20 of 93
Hale 12, 13, 11-sep 2024.jpg
September 23, 2024-New Hale Buildings
21 of 93
Sep.13.2024-A4 (1).jpg
September 13, 2024- TVA A4
22 of 93
hale 13-2024.jpg
September 12, 2024–Hale 13 Courtyard
23 of 93
A4-Sep 2024.png
September 13, 2024–TVA A4
24 of 93
July 13, 2024-Hales Interior Work.png
July 12, 2024–Hale 12, Framing and Plumbing/Hale 11, Slab Preparation/Hale 13, Utility Room Installation.
Planning, Design & Construction Department
25 of 93
Hale11-2024.png
July 03, 2024–Mid-Construction of Hale 11
Planning, Design & Construction Department
26 of 93
Hale2024.png
July 3, 2024-New Hale Buildings Interior Work
Planning, Design & Construction Department
27 of 93
Hale 13-2024.png
July 3, 2024-Hale 13 Building Outside Completion
Planning, Design & Construction Department
28 of 93
July 13, 2024-Hale 13.png
July 12, 2024–Aerial view of Hale 13 construction
Planning, Design & Construction Department
29 of 93
May 2024.png
May 10, 2024 - Hale 13: Construction Update.
Planning, Design & Construction Department
30 of 93
Hale 13-Courtyard.png
May 5, 2024-Hale 13 Courtyard
Planning, Design & Construction Department
31 of 93
May 2024-Hale 11.png
May 10, 2024- ICF installation for Hale 11.
Planning, Design & Construction Department
32 of 93
Hale 13-Common room and machine.png
May 02, 2024- Hale 13 Common Room 1 & Machines
Planning, Design & Construction Department
33 of 93
May 2024-Hale 12.png
May 10, 2024- Roofing work for Hale 12
Planning, Design & Construction Department
34 of 93
Project Overview-10.06.2023.png
October 6, 2023- Project Construction Overview
Planning, Design & Construction
35 of 93
Hale 11-10.06.2023.png
October 6, 2023- Elevator core preparation for Hale 11.
Planning, Design & Construction
36 of 93
Hale 12 side-10.06.2023.png
October 6, 2023- Installation of floor joists for the third-level construction of Hale 12.
Planning, Design & Construction
37 of 93
Hale 12-10.06.2023.png
October 6, 2023- Construction of the third floor for Hale 12.
Planning, Design & Construction
38 of 93
Hale 13 side 2-10.06.2023 .png
October 6, 2023- Hale 13 north side dry wall work.
Planning, Design & Construction
39 of 93
Hale 13-10.06.2023.png
October 6, 2023- Final stage of roof sheathing and tar installation
Planning, Design & Construction
40 of 93
August 2023-Hale 13.png
August 4, 2023-Hale 13 structure
Planning, Design & Construction
41 of 93
August 2023-Windows Hale 13.png
August 4, 2023-Hale 13 windows and awnings
Planning, Design & Construction
42 of 93
August 2023-Hale 12 Surf & Bike.png
August 4, 2023- Hale 12 surf and bike racks
Planning, Design & Construction
43 of 93
August 2023-Hale 12 & Hale 11.png
August 4, 2023- Hale 12 & 11 Boilers
Planning, Design & Construction
44 of 93
August 2023-Hale .png
August 4, 2023- Hale 12 elevator shaft
Planning, Design & Construction
45 of 93
June 2023-Hale 13- West Elevation.png
June 2023 - Hale 13 West Elevation
Planning, Design & Construction Department
46 of 93
June 2023-Hale 13- Courtyard & Elevated Walkway Concrete Pour.png
June 2023- Hale 13-Courtyard & Elevated Walkway Concrete
Planning, Design & Construction Department
47 of 93
June 2023-Hale 11 & 12.png
June 16, 2023-Hale 11 & 12 Footings
Planning, Design & Construction Department
48 of 93
June 2023-Hale 13 Aerial View.png
June 16, 2023-Hale 13 Roofing
Planning, Design & Construction Department
49 of 93
March 17, 2023-Hale 13.png
March 7, 2023 Update-Hale 13
Planning, Design & Construction
50 of 93
March 17, 2023-Hale 13 View 2.png
March 17, 2023-Hale 13 Update
Planning, Design & Construction
51 of 93
Hale 13 Precast Stairs-Feb 24, 2023.PNG
February 24, 2023- Hale 13 Precast Stairs
Planning, Design & Construction
52 of 93
Feb.17, 2023-Hale 11.png
February 17, 2023 (Hale 11 Aerial View)
Planning, Design & Construction Department
53 of 93
Feb.17, 2023-Hale 12.png
February 17, 2023- (Hale 12 Aerial View)
Planning, Design & Construction Department
54 of 93
Feb 17, 2023-Hale 13 Aerial View.png
February 17, 2023- (Hale 13 Aerial View)
Planning, Design & Construction Department
55 of 93
Feb 17, 2023-Hale Project Overview.png
February 17, 2023- (Hales Project Overview)
Planning, Design & Construction Department
56 of 93
Hale 12-Jan 27, 2023.png
January 12, 2023 - Hale 13 Top View
Planning, Design & Construction Department
57 of 93
Hale 11- Jan 27, 2023.png
January 27, 2023 - Hale 11 Top View
Planning, Design & Construction Department
58 of 93
Hale 13(closer view)-Jan 27, 2023.png
January 27, 2023 - Hale 13 Close Up View
Planning, Design & Construction Department
59 of 93
Hale 13-Jan 27, 2023.png
January 27, 2023- Hale 13 Top View
Planning, Design & Construction
60 of 93
Project Overview-January 27, 2023.png
January 27, 2023 (Project Overview for Hale 13, 12, & 11)
Planning, Design and Construction Department
61 of 93
Hale 13 January 13, 2023.png
January 13, 2023- Hale 13 (Insulated Concrete Form Walls and Scaffoldings)
Planning, Design & Construction Department
62 of 93
Hale 11-Dec 22, 2022.png
December 23, 2022- (Hale 11-Foot Plan)
Planning, Design & Construction
63 of 93
Hale 12-Dec 22, 2022.png
December 23, 2022- (Hale 12 Foot Plan-Tie Rebar)
Planning, Design & Construction
64 of 93
Hale 13-Dec 12, 2022.png
December 22, 2022-Hale 13 (Insulated Concrete Form Walls )
Planning, Design & Construction
65 of 93
Hale 13-Dec 22, 2022.png
December 23, 2022- (Hale 13 Area A Sequences 1-3) Project Overview
Planning, Design & Construction
66 of 93
Hale 11-13- Dec 22 2022.png
December 22, 2022- (Hale 11, 12, and 13 Construction Site Project Overview)
Planning, Design & Construction
67 of 93
Unit-Mock-Up-Nov 25, 2022.png
November 25, 2022- Unit Mock-Up Room-Project Overview
Planning, Design & Construction Department
68 of 93
Hale 11-Nov 25, 2022.png
November 25, 2022-Hale 13 Project Overview
Planning, Design & Construction
69 of 93
Hale 12-Nov 25, 2022.png
November 25, 2022- Hale 12 Project Overview
Planning, Design & Construction Department
70 of 93
Hale 13 Sequence- Nov 25, 2022.png
November 25, 2022-Hale 13 Sequence-Project Overview
Planning, Design & Construction
71 of 93
Hale 13-Nov 25, 2022.png
November 25, 2022- Hale 13 Construction Update
Planning, Design & Construction Department
72 of 93
Hale 13-Sequence 1-Nov 25, 2022.png
November 25, 2022-Hale 13 Sequence 1-Project Overview
Planning, Design & Construction Department
73 of 93
Project Overview Hale 11-13 (Nov 25, 2022).png
November 25, 2022- Project Overview
Planning, Design & Construction
74 of 93
Mock up room.PNG
Planning, Design & Construction Department
75 of 93
New Hale Update Photo 4.PNG
November 1, 2022 - Asphalt Paving First Lift North Roadway Completed
76 of 93
Hale 11-Footings 1.PNG
November 1, 2022 - Asphalt Paving First Lift North Roadway Completed
77 of 93
Hale 11 update.PNG
November 1, 2022 - Asphalt Paving First Lift North Roadway Completed
November 1, 2022 - Asphalt Paving First Lift North Roadway Completed
78 of 93
Hale 12.PNG
November 1, 2022 - Asphalt Paving First Lift North Roadway Completed
November 1, 2022 - Asphalt Paving First Lift North Roadway Completed
79 of 93
New Hale Update Photo 2.PNG
November 1, 2022 - Asphalt Paving First Lift North Roadway Completed
Planning, Design & Construction Department
80 of 93
New Hale Update Photo 1.PNG
November 1, 2022-Asphalt Paving First Lift North Roadway Completed
Planning, Design & Construction Department
81 of 93
3.29 Aerial looking towards the Temple
82 of 93
3.29 Aerial of Laie
83 of 93
3.29 Aerial Building Pads
84 of 93
03.15 Building Pad
85 of 93
03.15 Aerial of the Hales
86 of 93
03.15 Aerial of Laie
87 of 93
03.10 Aerial of Hales Old and New
88 of 93
03-10 East View Ground Prep
89 of 93
03-10 Leveling and Pouring dirt
90 of 93
03-10 South View Sites
91 of 93
03.02 Hale Groundwork
93 of 93
03.02 First Hale