New Hale Buildings
1 of 4
New Hales 11-13
2 of 4
Side Rendering of New Hales
3 of 4
New Hales 11-13 Project
4 of 4
Hales 11-13 locations
1
of
4
About This Project
Additional on-campus housing for single students will be located behind the current single-student hales. These new hales will serve as single student dormitories. These hales are apartment-style buildings similar to Hales 4, 5, 6, 7, and 10. They will be four stories high and will accommodate six students per room. Each floor will have approximately fourteen units. The new project will add housing for 900 to 1,000 single students. These hales will also be equipped with surf/bike racks.
1 of 9
Nov. 2024, Hale 11.jpg
Planning, Design & Construction Department
2 of 9
Nov. 2024-Hale 11-Interior.jpg
Planning, Design & Construction Department
3 of 9
Surf & Bike racks 2024.jpg
Planning, Design & Construction Department
4 of 9
Hale 12-Nov. 2024.jpg
Planning, Design & Construction Department
5 of 9
Hale 13-Novmeber 2024.jpg
Planning, Design & Construction Department
6 of 9
Dec. 2024-Hale 13.JPG
Planning, Design & Construction Department
7 of 9
Hale 13-Dec 2024.JPG
Planning, Design & Construction Department
8 of 9
Dec. 2024-Hale 12.JPG
Planning, Design & Construction Department
9 of 9
Hale 12-Dec 2024.JPG
Planning, Design & Construction Department
1
of
9
Timeline and Updates of the Project
Completion Date
Hale 13 - February 2025
Hale 12 - June 2025
Hale 11 - November 2024
Recent Update
December 2024
- Hale 11
- Students have moved into the building; work orders are being resolved.
- Hale 12:
- Bike and surf storage areas are being built.
- Gutters and water drainage systems have been installed and painted.
- Furniture is being set up inside the building.
- Preparations are underway to add decorative finishes to courtyard columns and to pour a new sidewalk in January.
- Hale 13
- The outdoor lanai (patio) was completed on December 19.
- The roof is almost finished, and waterproofing work is in progress.
- Windows and doors are being readied for installation.
Construction Gallery
1 of 83
03.02 First Hale
2 of 83
03.02 Ground
3 of 83
03.02 Hale Groundwork
4 of 83
03-10 South View Sites
5 of 83
03-10 Leveling and Pouring dirt
6 of 83
03-10 East View Ground Prep
7 of 83
03.10 Aerial of Hales Old and New
8 of 83
03.15 Aerial of Laie
9 of 83
03.15 Aerial of the Hales
10 of 83
03.15 Building Pad
11 of 83
3.29 Aerial Building Pads
12 of 83
3.29 Aerial of Laie
13 of 83
3.29 Aerial looking towards the Temple
14 of 83
New Hale Update Photo 1.PNG
Planning, Design & Construction Department
15 of 83
New Hale Update Photo 2.PNG
Planning, Design & Construction Department
16 of 83
Hale 12.PNG
November 1, 2022 - Asphalt Paving First Lift North Roadway Completed
17 of 83
Hale 11 update.PNG
November 1, 2022 - Asphalt Paving First Lift North Roadway Completed
18 of 83
Hale 11-Footings 1.PNG
19 of 83
New Hale Update Photo 4.PNG
20 of 83
Mock up room.PNG
Planning, Design & Construction Department
21 of 83
Project Overview Hale 11-13 (Nov 25, 2022).png
Planning, Design & Construction
22 of 83
Hale 13-Sequence 1-Nov 25, 2022.png
Planning, Design & Construction Department
23 of 83
Hale 13-Nov 25, 2022.png
Planning, Design & Construction Department
24 of 83
Hale 13 Sequence- Nov 25, 2022.png
Planning, Design & Construction
25 of 83
Hale 12-Nov 25, 2022.png
Planning, Design & Construction Department
26 of 83
Hale 11-Nov 25, 2022.png
Planning, Design & Construction
27 of 83
Unit-Mock-Up-Nov 25, 2022.png
Planning, Design & Construction Department
28 of 83
Hale 11-13- Dec 22 2022.png
Planning, Design & Construction
29 of 83
Hale 13-Dec 22, 2022.png
Planning, Design & Construction
30 of 83
Hale 13-Dec 12, 2022.png
Planning, Design & Construction
31 of 83
Hale 12-Dec 22, 2022.png
Planning, Design & Construction
32 of 83
Hale 11-Dec 22, 2022.png
Planning, Design & Construction
33 of 83
Hale 13 January 13, 2023.png
Planning, Design & Construction Department
34 of 83
Project Overview-January 27, 2023.png
Planning, Design and Construction Department
35 of 83
Hale 13-Jan 27, 2023.png
Planning, Design & Construction
36 of 83
Hale 13(closer view)-Jan 27, 2023.png
Planning, Design & Construction Department
37 of 83
Hale 11- Jan 27, 2023.png
Planning, Design & Construction Department
38 of 83
Hale 12-Jan 27, 2023.png
Planning, Design & Construction Department
39 of 83
Feb 17, 2023-Hale Project Overview.png
Planning, Design & Construction Department
40 of 83
Feb 17, 2023-Hale 13 Aerial View.png
Planning, Design & Construction Department
41 of 83
Feb.17, 2023-Hale 12.png
Planning, Design & Construction Department
42 of 83
Feb.17, 2023-Hale 11.png
Planning, Design & Construction Department
43 of 83
Hale 13 Precast Stairs-Feb 24, 2023.PNG
Planning, Design & Construction
44 of 83
March 17, 2023-Hale 13 View 2.png
Planning, Design & Construction
45 of 83
March 17, 2023-Hale 13.png
Planning, Design & Construction
46 of 83
June 2023-Hale 13 Aerial View.png
Planning, Design & Construction Department
47 of 83
June 2023-Hale 11 & 12.png
Planning, Design & Construction Department
48 of 83
June 2023-Hale 13- Courtyard & Elevated Walkway Concrete Pour.png
Planning, Design & Construction Department
49 of 83
June 2023-Hale 13- West Elevation.png
Planning, Design & Construction Department
50 of 83
August 2023-Hale .png
Planning, Design & Construction
51 of 83
August 2023-Hale 12 & Hale 11.png
Planning, Design & Construction
52 of 83
August 2023-Hale 12 Surf & Bike.png
Planning, Design & Construction
53 of 83
August 2023-Windows Hale 13.png
Planning, Design & Construction
54 of 83
August 2023-Hale 13.png
Planning, Design & Construction
55 of 83
Hale 13-10.06.2023.png
Planning, Design & Construction
56 of 83
Hale 13 side 2-10.06.2023 .png
Planning, Design & Construction
57 of 83
Hale 12-10.06.2023.png
Planning, Design & Construction
58 of 83
Hale 12 side-10.06.2023.png
Planning, Design & Construction
59 of 83
Hale 11-10.06.2023.png
Planning, Design & Construction
60 of 83
Project Overview-10.06.2023.png
Planning, Design & Construction
61 of 83
May 2024-Hale 12.png
Planning, Design & Construction Department
62 of 83
Hale 13-Common room and machine.png
Planning, Design & Construction Department
63 of 83
May 2024-Hale 11.png
Planning, Design & Construction Department
64 of 83
Hale 13-Courtyard.png
Planning, Design & Construction Department
65 of 83
May 2024.png
Planning, Design & Construction Department
66 of 83
July 13, 2024-Hale 13.png
Planning, Design & Construction Department
67 of 83
Hale 13-2024.png
Planning, Design & Construction Department
68 of 83
Hale2024.png
Planning, Design & Construction Department
69 of 83
Hale11-2024.png
Planning, Design & Construction Department
70 of 83
July 13, 2024-Hales Interior Work.png
Planning, Design & Construction Department
71 of 83
A4-Sep 2024.png
72 of 83
hale 13-2024.jpg
73 of 83
Sep.13.2024-A4 (1).jpg
74 of 83
Hale 12, 13, 11-sep 2024.jpg
75 of 83
Hale 11-sep 2024.jpg
76 of 83
Hale 12-Sep 2024.jpg
77 of 83
Hale 13 common area.png
78 of 83
Hale 13 Living room.png
79 of 83
Hale 13-Aerial View.jpg
80 of 83
Nov. 2024-Hale 11-Interior.jpg
Planning, Design & Construction Department
81 of 83
Hale 12-Nov. 2024.jpg
Planning, Design & Construction Department
82 of 83
Hale 13-Novmeber 2024.jpg
Planning, Design & Construction Department
83 of 83
Nov. 2024, Hale 11.jpg
Planning, Design & Construction Department
1
of
83