New Hale Buildings
1 of 4
New Hales 11-13
Rendering of the New Hale Building
2 of 4
Side Rendering of New Hales
Side Rendering of New Hale Buildings
3 of 4
New Hales 11-13 Project
Front Rendering of New Hale Buildings
4 of 4
Hales 11-13 locations
The Location for the Projected New Hale Buildings
1
of
4
About This Project
Additional on-campus housing for single students will be located behind the current single-student hales. These new hales will serve as single student dormitories. These hales are apartment-style buildings similar to Hales 4, 5, 6, 7, and 10. They will be four stories high and will accommodate six students per room. Each floor will have approximately fourteen units. The new project will add housing for 900 to 1,000 single students. These hales will also be equipped with surf/bike racks.
1 of 9
April 2025-Hale 12.JPG
April 2025—Hale 12
Planning, Design & Construction Department
2 of 9
April 2025-Hale 13.JPG
April 2025—Hale 13
Planning, Design & Construction Department
3 of 9
April 2025-courtyard.JPG
April 2025—Plaza
Planning, Design & Construction Department
4 of 9
New Hale Site-March 2025.JPG
March 2025—New Hale Buildings
Planning, Design, & Construction Department
5 of 9
Hale 12-March 2025.JPG
March 2025—Hale 12
Planning, Design, & Construction Department
6 of 9
Roof-Hale 12-March 2025.JPG
March 2025–Hale 12
Planning, Design & Construction Department
7 of 9
March 2025-Hale 12.jpg
March 2025—Hale 12
Planning, Design & Construction Department
8 of 9
Hale 13- March 2025.JPG
March 2025—Hale 13
Planning, Design & Construction Department
9 of 9
Hale 13-March 2025.JPG
March 2025—Hale 13
Planning, Design, & Construction Department
1
of
9
Timeline and Updates of the Project
Completion Date
Hale 13–February 2026
Hale 12–June 2025
Hale 11–November 2024
Recent Update
April 2025
Hales 11-13
Hale 12
- All exterior landscaping walls and slabs have been placed around the building.
- Concrete slabs between Hale 12 and Hale 13 continue to be placed.
- Light poles continue to be installed around the building.
- The building has been pressure-washed, and interior cleaning of all the units is in progress.
- Automatic door openers are being installed at security gates.
Hale 13
- Stucco has been applied and painted on the exterior around levels 2-4.
- Cabinets have been fully installed on the North side of the building.
- Drywall work is nearly complete on levels 3-4 of the South side of the building.
- Window awning installation is complete.
- Stucco has been applied and painted on the upper 3 levels of the exterior walls.
- Appliances are being installed in units on the north side of the building.
Construction Gallery
1 of 94
03.02 First Hale
2 of 94
03.02 Ground
3 of 94
03.02 Hale Groundwork
4 of 94
03-10 South View Sites
5 of 94
03-10 Leveling and Pouring dirt
6 of 94
03-10 East View Ground Prep
7 of 94
03.10 Aerial of Hales Old and New
8 of 94
03.15 Aerial of Laie
9 of 94
03.15 Aerial of the Hales
10 of 94
03.15 Building Pad
11 of 94
3.29 Aerial Building Pads
12 of 94
3.29 Aerial of Laie
13 of 94
3.29 Aerial looking towards the Temple
14 of 94
New Hale Update Photo 1.PNG
November 1, 2022-Asphalt Paving First Lift North Roadway Completed
Planning, Design & Construction Department
15 of 94
New Hale Update Photo 2.PNG
November 1, 2022 - Asphalt Paving First Lift North Roadway Completed
Planning, Design & Construction Department
16 of 94
Hale 12.PNG
November 1, 2022 - Asphalt Paving First Lift North Roadway Completed
November 1, 2022 - Asphalt Paving First Lift North Roadway Completed
17 of 94
Hale 11 update.PNG
November 1, 2022 - Asphalt Paving First Lift North Roadway Completed
November 1, 2022 - Asphalt Paving First Lift North Roadway Completed
18 of 94
Hale 11-Footings 1.PNG
November 1, 2022 - Asphalt Paving First Lift North Roadway Completed
19 of 94
New Hale Update Photo 4.PNG
November 1, 2022 - Asphalt Paving First Lift North Roadway Completed
20 of 94
Mock up room.PNG
Planning, Design & Construction Department
21 of 94
Project Overview Hale 11-13 (Nov 25, 2022).png
November 25, 2022- Project Overview
Planning, Design & Construction
22 of 94
Hale 13-Sequence 1-Nov 25, 2022.png
November 25, 2022-Hale 13 Sequence 1-Project Overview
Planning, Design & Construction Department
23 of 94
Hale 13-Nov 25, 2022.png
November 25, 2022- Hale 13 Construction Update
Planning, Design & Construction Department
24 of 94
Hale 13 Sequence- Nov 25, 2022.png
November 25, 2022-Hale 13 Sequence-Project Overview
Planning, Design & Construction
25 of 94
Hale 12-Nov 25, 2022.png
November 25, 2022- Hale 12 Project Overview
Planning, Design & Construction Department
26 of 94
Hale 11-Nov 25, 2022.png
November 25, 2022-Hale 13 Project Overview
Planning, Design & Construction
27 of 94
Unit-Mock-Up-Nov 25, 2022.png
November 25, 2022- Unit Mock-Up Room-Project Overview
Planning, Design & Construction Department
28 of 94
Hale 11-13- Dec 22 2022.png
December 22, 2022- (Hale 11, 12, and 13 Construction Site Project Overview)
Planning, Design & Construction
29 of 94
Hale 13-Dec 22, 2022.png
December 23, 2022- (Hale 13 Area A Sequences 1-3) Project Overview
Planning, Design & Construction
30 of 94
Hale 13-Dec 12, 2022.png
December 22, 2022-Hale 13 (Insulated Concrete Form Walls )
Planning, Design & Construction
31 of 94
Hale 12-Dec 22, 2022.png
December 23, 2022- (Hale 12 Foot Plan-Tie Rebar)
Planning, Design & Construction
32 of 94
Hale 11-Dec 22, 2022.png
December 23, 2022- (Hale 11-Foot Plan)
Planning, Design & Construction
33 of 94
Hale 13 January 13, 2023.png
January 13, 2023- Hale 13 (Insulated Concrete Form Walls and Scaffoldings)
Planning, Design & Construction Department
34 of 94
Project Overview-January 27, 2023.png
January 27, 2023 (Project Overview for Hale 13, 12, & 11)
Planning, Design and Construction Department
35 of 94
Hale 13-Jan 27, 2023.png
January 27, 2023- Hale 13 Top View
Planning, Design & Construction
36 of 94
Hale 13(closer view)-Jan 27, 2023.png
January 27, 2023 - Hale 13 Close Up View
Planning, Design & Construction Department
37 of 94
Hale 11- Jan 27, 2023.png
January 27, 2023 - Hale 11 Top View
Planning, Design & Construction Department
38 of 94
Hale 12-Jan 27, 2023.png
January 12, 2023 - Hale 13 Top View
Planning, Design & Construction Department
39 of 94
Feb 17, 2023-Hale Project Overview.png
February 17, 2023- (Hales Project Overview)
Planning, Design & Construction Department
40 of 94
Feb 17, 2023-Hale 13 Aerial View.png
February 17, 2023- (Hale 13 Aerial View)
Planning, Design & Construction Department
41 of 94
Feb.17, 2023-Hale 12.png
February 17, 2023- (Hale 12 Aerial View)
Planning, Design & Construction Department
42 of 94
Feb.17, 2023-Hale 11.png
February 17, 2023 (Hale 11 Aerial View)
Planning, Design & Construction Department
43 of 94
Hale 13 Precast Stairs-Feb 24, 2023.PNG
February 24, 2023- Hale 13 Precast Stairs
Planning, Design & Construction
44 of 94
March 17, 2023-Hale 13 View 2.png
March 17, 2023-Hale 13 Update
Planning, Design & Construction
45 of 94
March 17, 2023-Hale 13.png
March 7, 2023 Update-Hale 13
Planning, Design & Construction
46 of 94
June 2023-Hale 13 Aerial View.png
June 16, 2023-Hale 13 Roofing
Planning, Design & Construction Department
47 of 94
June 2023-Hale 11 & 12.png
June 16, 2023-Hale 11 & 12 Footings
Planning, Design & Construction Department
48 of 94
June 2023-Hale 13- Courtyard & Elevated Walkway Concrete Pour.png
June 2023- Hale 13-Courtyard & Elevated Walkway Concrete
Planning, Design & Construction Department
49 of 94
June 2023-Hale 13- West Elevation.png
June 2023 - Hale 13 West Elevation
Planning, Design & Construction Department
50 of 94
August 2023-Hale .png
August 4, 2023- Hale 12 elevator shaft
Planning, Design & Construction
51 of 94
August 2023-Hale 12 & Hale 11.png
August 4, 2023- Hale 12 & 11 Boilers
Planning, Design & Construction
52 of 94
August 2023-Hale 12 Surf & Bike.png
August 4, 2023- Hale 12 surf and bike racks
Planning, Design & Construction
53 of 94
August 2023-Windows Hale 13.png
August 4, 2023-Hale 13 windows and awnings
Planning, Design & Construction
54 of 94
August 2023-Hale 13.png
August 4, 2023-Hale 13 structure
Planning, Design & Construction
55 of 94
Hale 13-10.06.2023.png
October 6, 2023- Final stage of roof sheathing and tar installation
Planning, Design & Construction
56 of 94
Hale 13 side 2-10.06.2023 .png
October 6, 2023- Hale 13 north side dry wall work.
Planning, Design & Construction
57 of 94
Hale 12-10.06.2023.png
October 6, 2023- Construction of the third floor for Hale 12.
Planning, Design & Construction
58 of 94
Hale 12 side-10.06.2023.png
October 6, 2023- Installation of floor joists for the third-level construction of Hale 12.
Planning, Design & Construction
59 of 94
Hale 11-10.06.2023.png
October 6, 2023- Elevator core preparation for Hale 11.
Planning, Design & Construction
60 of 94
Project Overview-10.06.2023.png
October 6, 2023- Project Construction Overview
Planning, Design & Construction
61 of 94
May 2024-Hale 12.png
May 10, 2024- Roofing work for Hale 12
Planning, Design & Construction Department
62 of 94
Hale 13-Common room and machine.png
May 02, 2024- Hale 13 Common Room 1 & Machines
Planning, Design & Construction Department
63 of 94
May 2024-Hale 11.png
May 10, 2024- ICF installation for Hale 11.
Planning, Design & Construction Department
64 of 94
Hale 13-Courtyard.png
May 5, 2024-Hale 13 Courtyard
Planning, Design & Construction Department
65 of 94
May 2024.png
May 10, 2024 - Hale 13: Construction Update.
Planning, Design & Construction Department
66 of 94
July 13, 2024-Hale 13.png
July 12, 2024–Aerial view of Hale 13 construction
Planning, Design & Construction Department
67 of 94
Hale 13-2024.png
July 3, 2024-Hale 13 Building Outside Completion
Planning, Design & Construction Department
68 of 94
Hale2024.png
July 3, 2024-New Hale Buildings Interior Work
Planning, Design & Construction Department
69 of 94
Hale11-2024.png
July 03, 2024–Mid-Construction of Hale 11
Planning, Design & Construction Department
70 of 94
July 13, 2024-Hales Interior Work.png
July 12, 2024–Hale 12, Framing and Plumbing/Hale 11, Slab Preparation/Hale 13, Utility Room Installation.
Planning, Design & Construction Department
71 of 94
A4-Sep 2024.png
September 13, 2024–TVA A4
72 of 94
hale 13-2024.jpg
September 12, 2024–Hale 13 Courtyard
73 of 94
Sep.13.2024-A4 (1).jpg
September 13, 2024- TVA A4
74 of 94
Hale 12, 13, 11-sep 2024.jpg
September 23, 2024-New Hale Buildings
75 of 94
Hale 11-sep 2024.jpg
September 23, 2024-Hale 11
76 of 94
Hale 12-Sep 2024.jpg
September 23, 2024–Hale 12
77 of 94
Hale 13 common area.png
September 23, 2024–Common Room
78 of 94
Hale 13 Living room.png
September 23, 2024–Living Area Space
79 of 94
Nov. 2024, Hale 11.jpg
November 2024–Hale 11
Planning, Design & Construction Department
80 of 94
Hale 13-Aerial View.jpg
September 12, 2024-Hale 13
81 of 94
Nov. 2024-Hale 11-Interior.jpg
Hale 11
Planning, Design & Construction Department
82 of 94
Hale 12-Nov. 2024.jpg
November 2024–Hale 12
Planning, Design & Construction Department
83 of 94
Hale 13-Novmeber 2024.jpg
November 2024–Hale 13
Planning, Design & Construction Department
84 of 94
Dec. 2024-TVA Phase 2.jpg
December 2024–TVA Phase 2
Planning, Design & Construction Department
85 of 94
Dec. 2024-Hale 12.JPG
December 2024–Hale 12
Planning, Design & Construction Department
86 of 94
Hale 12-Dec 2024.JPG
December 2024–Hale 12
Planning, Design & Construction Department
87 of 94
Surf & Bike racks 2024.jpg
November 2024–Hale 11
Planning, Design & Construction Department
88 of 94
Dec. 2024-Hale 13.JPG
December 2024–Hale 13
Planning, Design & Construction Department
89 of 94
Hale 12 & Hale 13-Feb 2025.jpg
February 2025–Campus New Hales
Planning, Design & Construction Department
90 of 94
Hale 13-Feb 2025.jpg
February 2025–Hale 13
Planning, Design & Construction Department
91 of 94
Hale 12 Backside-Feb 2025.jpg
February 2025–Hale 12
Planning, Design & Construction Department
92 of 94
Hale 12-Feb 2025.jpg
February 2025–Hale 12
Planning, Design & Construction Department
93 of 94
Hale 13 Front-Feb 2025.jpg
February 2025–Hale 13
Planning, Design & Construction Department
94 of 94
Project Overview-New Hales.jpg
February 2025–Project Overview of New Hales
Planning, Design & Construction Department
1
of
94