New Hale Buildings

1 of 4
New Hales 11-13
Rendering of the New Hale Building

2 of 4
Side Rendering of New Hales
Side Rendering of New Hale Buildings

3 of 4
New Hales 11-13 Project
Front Rendering of New Hale Buildings
4 of 4
Hales 11-13 locations
The Location for the Projected New Hale Buildings
1
of
4
About This Project
Additional on-campus housing for single students will be located behind the current single-student hales. These new hales will serve as single student dormitories. These hales are apartment-style buildings similar to Hales 4, 5, 6, 7, and 10. They will be four stories high and will accommodate six students per room. Each floor will have approximately fourteen units. The new project will add housing for 900 to 1,000 single students. These hales will also be equipped with surf/bike racks.

1 of 9
Nov. 2024, Hale 11.jpg
November 2024–Hale 11
Planning, Design & Construction Department

2 of 9
Nov. 2024-Hale 11-Interior.jpg
Hale 11
Planning, Design & Construction Department

3 of 9
Surf & Bike racks 2024.jpg
November 2024–Hale 11
Planning, Design & Construction Department

4 of 9
Hale 12-Nov. 2024.jpg
November 2024–Hale 12
Planning, Design & Construction Department

5 of 9
Hale 13-Novmeber 2024.jpg
November 2024–Hale 13
Planning, Design & Construction Department
6 of 9
Dec. 2024-Hale 13.JPG
December 2024–Hale 13
Planning, Design & Construction Department
7 of 9
Hale 13-Dec 2024.JPG
December 2024–Hale 13
Planning, Design & Construction Department
8 of 9
Dec. 2024-Hale 12.JPG
December 2024–Hale 12
Planning, Design & Construction Department
9 of 9
Hale 12-Dec 2024.JPG
December 2024–Hale 12
Planning, Design & Construction Department
1
of
9
Timeline and Updates of the Project
Completion Date
Hale 13 - February 2025
Hale 12 - June 2025
Hale 11 - November 2024
Recent Update
December 2024
- Hale 11
- Students have moved into the building; work orders are being resolved.
- Hale 12:
- Bike and surf storage areas are being built.
- Gutters and water drainage systems have been installed and painted.
- Furniture is being set up inside the building.
- Preparations are underway to add decorative finishes to courtyard columns and to pour a new sidewalk in January.
- Hale 13
- The outdoor lanai (patio) was completed on December 19.
- The roof is almost finished, and waterproofing work is in progress.
- Windows and doors are being readied for installation.
Construction Gallery
1 of 83
03.02 First Hale
2 of 83
03.02 Ground
3 of 83
03.02 Hale Groundwork
4 of 83
03-10 South View Sites
5 of 83
03-10 Leveling and Pouring dirt
6 of 83
03-10 East View Ground Prep
7 of 83
03.10 Aerial of Hales Old and New
8 of 83
03.15 Aerial of Laie
9 of 83
03.15 Aerial of the Hales
10 of 83
03.15 Building Pad
11 of 83
3.29 Aerial Building Pads
12 of 83
3.29 Aerial of Laie
13 of 83
3.29 Aerial looking towards the Temple
14 of 83
New Hale Update Photo 1.PNG
November 1, 2022-Asphalt Paving First Lift North Roadway Completed
Planning, Design & Construction Department
15 of 83
New Hale Update Photo 2.PNG
November 1, 2022 - Asphalt Paving First Lift North Roadway Completed
Planning, Design & Construction Department
16 of 83
Hale 12.PNG
November 1, 2022 - Asphalt Paving First Lift North Roadway Completed
November 1, 2022 - Asphalt Paving First Lift North Roadway Completed
17 of 83
Hale 11 update.PNG
November 1, 2022 - Asphalt Paving First Lift North Roadway Completed
November 1, 2022 - Asphalt Paving First Lift North Roadway Completed
18 of 83
Hale 11-Footings 1.PNG
November 1, 2022 - Asphalt Paving First Lift North Roadway Completed
19 of 83
New Hale Update Photo 4.PNG
November 1, 2022 - Asphalt Paving First Lift North Roadway Completed
20 of 83
Mock up room.PNG
Planning, Design & Construction Department

21 of 83
Project Overview Hale 11-13 (Nov 25, 2022).png
November 25, 2022- Project Overview
Planning, Design & Construction

22 of 83
Hale 13-Sequence 1-Nov 25, 2022.png
November 25, 2022-Hale 13 Sequence 1-Project Overview
Planning, Design & Construction Department

23 of 83
Hale 13-Nov 25, 2022.png
November 25, 2022- Hale 13 Construction Update
Planning, Design & Construction Department

24 of 83
Hale 13 Sequence- Nov 25, 2022.png
November 25, 2022-Hale 13 Sequence-Project Overview
Planning, Design & Construction

25 of 83
Hale 12-Nov 25, 2022.png
November 25, 2022- Hale 12 Project Overview
Planning, Design & Construction Department

26 of 83
Hale 11-Nov 25, 2022.png
November 25, 2022-Hale 13 Project Overview
Planning, Design & Construction

27 of 83
Unit-Mock-Up-Nov 25, 2022.png
November 25, 2022- Unit Mock-Up Room-Project Overview
Planning, Design & Construction Department

28 of 83
Hale 11-13- Dec 22 2022.png
December 22, 2022- (Hale 11, 12, and 13 Construction Site Project Overview)
Planning, Design & Construction

29 of 83
Hale 13-Dec 22, 2022.png
December 23, 2022- (Hale 13 Area A Sequences 1-3) Project Overview
Planning, Design & Construction

30 of 83
Hale 13-Dec 12, 2022.png
December 22, 2022-Hale 13 (Insulated Concrete Form Walls )
Planning, Design & Construction

31 of 83
Hale 12-Dec 22, 2022.png
December 23, 2022- (Hale 12 Foot Plan-Tie Rebar)
Planning, Design & Construction

32 of 83
Hale 11-Dec 22, 2022.png
December 23, 2022- (Hale 11-Foot Plan)
Planning, Design & Construction

33 of 83
Hale 13 January 13, 2023.png
January 13, 2023- Hale 13 (Insulated Concrete Form Walls and Scaffoldings)
Planning, Design & Construction Department

34 of 83
Project Overview-January 27, 2023.png
January 27, 2023 (Project Overview for Hale 13, 12, & 11)
Planning, Design and Construction Department

35 of 83
Hale 13-Jan 27, 2023.png
January 27, 2023- Hale 13 Top View
Planning, Design & Construction

36 of 83
Hale 13(closer view)-Jan 27, 2023.png
January 27, 2023 - Hale 13 Close Up View
Planning, Design & Construction Department

37 of 83
Hale 11- Jan 27, 2023.png
January 27, 2023 - Hale 11 Top View
Planning, Design & Construction Department

38 of 83
Hale 12-Jan 27, 2023.png
January 12, 2023 - Hale 13 Top View
Planning, Design & Construction Department

39 of 83
Feb 17, 2023-Hale Project Overview.png
February 17, 2023- (Hales Project Overview)
Planning, Design & Construction Department

40 of 83
Feb 17, 2023-Hale 13 Aerial View.png
February 17, 2023- (Hale 13 Aerial View)
Planning, Design & Construction Department

41 of 83
Feb.17, 2023-Hale 12.png
February 17, 2023- (Hale 12 Aerial View)
Planning, Design & Construction Department

42 of 83
Feb.17, 2023-Hale 11.png
February 17, 2023 (Hale 11 Aerial View)
Planning, Design & Construction Department
43 of 83
Hale 13 Precast Stairs-Feb 24, 2023.PNG
February 24, 2023- Hale 13 Precast Stairs
Planning, Design & Construction

44 of 83
March 17, 2023-Hale 13 View 2.png
March 17, 2023-Hale 13 Update
Planning, Design & Construction

45 of 83
March 17, 2023-Hale 13.png
March 7, 2023 Update-Hale 13
Planning, Design & Construction

46 of 83
June 2023-Hale 13 Aerial View.png
June 16, 2023-Hale 13 Roofing
Planning, Design & Construction Department

47 of 83
June 2023-Hale 11 & 12.png
June 16, 2023-Hale 11 & 12 Footings
Planning, Design & Construction Department

48 of 83
June 2023-Hale 13- Courtyard & Elevated Walkway Concrete Pour.png
June 2023- Hale 13-Courtyard & Elevated Walkway Concrete
Planning, Design & Construction Department

49 of 83
June 2023-Hale 13- West Elevation.png
June 2023 - Hale 13 West Elevation
Planning, Design & Construction Department

50 of 83
August 2023-Hale .png
August 4, 2023- Hale 12 elevator shaft
Planning, Design & Construction

51 of 83
August 2023-Hale 12 & Hale 11.png
August 4, 2023- Hale 12 & 11 Boilers
Planning, Design & Construction

52 of 83
August 2023-Hale 12 Surf & Bike.png
August 4, 2023- Hale 12 surf and bike racks
Planning, Design & Construction

53 of 83
August 2023-Windows Hale 13.png
August 4, 2023-Hale 13 windows and awnings
Planning, Design & Construction

54 of 83
August 2023-Hale 13.png
August 4, 2023-Hale 13 structure
Planning, Design & Construction

55 of 83
Hale 13-10.06.2023.png
October 6, 2023- Final stage of roof sheathing and tar installation
Planning, Design & Construction

56 of 83
Hale 13 side 2-10.06.2023 .png
October 6, 2023- Hale 13 north side dry wall work.
Planning, Design & Construction

57 of 83
Hale 12-10.06.2023.png
October 6, 2023- Construction of the third floor for Hale 12.
Planning, Design & Construction

58 of 83
Hale 12 side-10.06.2023.png
October 6, 2023- Installation of floor joists for the third-level construction of Hale 12.
Planning, Design & Construction

59 of 83
Hale 11-10.06.2023.png
October 6, 2023- Elevator core preparation for Hale 11.
Planning, Design & Construction

60 of 83
Project Overview-10.06.2023.png
October 6, 2023- Project Construction Overview
Planning, Design & Construction

61 of 83
May 2024-Hale 12.png
May 10, 2024- Roofing work for Hale 12
Planning, Design & Construction Department

62 of 83
Hale 13-Common room and machine.png
May 02, 2024- Hale 13 Common Room 1 & Machines
Planning, Design & Construction Department

63 of 83
May 2024-Hale 11.png
May 10, 2024- ICF installation for Hale 11.
Planning, Design & Construction Department

64 of 83
Hale 13-Courtyard.png
May 5, 2024-Hale 13 Courtyard
Planning, Design & Construction Department

65 of 83
May 2024.png
May 10, 2024 - Hale 13: Construction Update.
Planning, Design & Construction Department

66 of 83
July 13, 2024-Hale 13.png
July 12, 2024–Aerial view of Hale 13 construction
Planning, Design & Construction Department

67 of 83
Hale 13-2024.png
July 3, 2024-Hale 13 Building Outside Completion
Planning, Design & Construction Department

68 of 83
Hale2024.png
July 3, 2024-New Hale Buildings Interior Work
Planning, Design & Construction Department

69 of 83
Hale11-2024.png
July 03, 2024–Mid-Construction of Hale 11
Planning, Design & Construction Department

70 of 83
July 13, 2024-Hales Interior Work.png
July 12, 2024–Hale 12, Framing and Plumbing/Hale 11, Slab Preparation/Hale 13, Utility Room Installation.
Planning, Design & Construction Department

71 of 83
A4-Sep 2024.png
September 13, 2024–TVA A4

72 of 83
hale 13-2024.jpg
September 12, 2024–Hale 13 Courtyard

73 of 83
Sep.13.2024-A4 (1).jpg
September 13, 2024- TVA A4

74 of 83
Hale 12, 13, 11-sep 2024.jpg
September 23, 2024-New Hale Buildings

75 of 83
Hale 11-sep 2024.jpg
September 23, 2024-Hale 11

76 of 83
Hale 12-Sep 2024.jpg
September 23, 2024–Hale 12

77 of 83
Hale 13 common area.png
September 23, 2024–Common Room

78 of 83
Hale 13 Living room.png
September 23, 2024–Living Area Space

79 of 83
Hale 13-Aerial View.jpg
September 12, 2024-Hale 13

80 of 83
Nov. 2024-Hale 11-Interior.jpg
Hale 11
Planning, Design & Construction Department

81 of 83
Hale 12-Nov. 2024.jpg
November 2024–Hale 12
Planning, Design & Construction Department

82 of 83
Hale 13-Novmeber 2024.jpg
November 2024–Hale 13
Planning, Design & Construction Department

83 of 83
Nov. 2024, Hale 11.jpg
November 2024–Hale 11
Planning, Design & Construction Department
1
of
83