New Hale Buildings

1 of 4
New Hales 11-13
Rendering of the New Hale Building

2 of 4
Side Rendering of New Hales
Side Rendering of New Hale Buildings

3 of 4
New Hales 11-13 Project
Front Rendering of New Hale Buildings
4 of 4
Hales 11-13 locations
The Location for the Projected New Hale Buildings
1
of
4

1 of 4
New Hales 11-13
Rendering of the New Hale Building

2 of 4
Side Rendering of New Hales
Side Rendering of New Hale Buildings

3 of 4
New Hales 11-13 Project
Front Rendering of New Hale Buildings
4 of 4
Hales 11-13 locations
The Location for the Projected New Hale Buildings
1
of
4
About this Project
Additional on-campus housing for single students will be located behind the current single-student hales. These new hales will serve as single student dormitories. These Hales are apartment-style buildings similar to Hales 4, 5, 6, 7, and 10. They will be four stories high and will accommodate six students per room. Each floor will have approximately fourteen units. The new project will add housing for 900-1,000 single students. These Hales will also be equipped with Surf/Bike racks.

1 of 5
Hale 11-13- Dec 22 2022.png
December 22, 2022- (Hale 11, 12, and 13 Construction Site Project Overview)
Planning, Design & Construction

2 of 5
Hale 13-Dec 22, 2022.png
December 23, 2022- (Hale 13 Area A Sequences 1-3) Project Overview
Planning, Design & Construction

3 of 5
Hale 13-Dec 12, 2022.png
December 22, 2022-Hale 13 (Insulated Concrete Form Walls )
Planning, Design & Construction

4 of 5
Hale 12-Dec 22, 2022.png
December 23, 2022- (Hale 12 Foot Plan-Tie Rebar)
Planning, Design & Construction

5 of 5
Hale 11-Dec 22, 2022.png
December 23, 2022- (Hale 11-Foot Plan)
Planning, Design & Construction
1
of
5

1 of 5
Hale 11-13- Dec 22 2022.png
December 22, 2022- (Hale 11, 12, and 13 Construction Site Project Overview)
Planning, Design & Construction

2 of 5
Hale 13-Dec 22, 2022.png
December 23, 2022- (Hale 13 Area A Sequences 1-3) Project Overview
Planning, Design & Construction

3 of 5
Hale 13-Dec 12, 2022.png
December 22, 2022-Hale 13 (Insulated Concrete Form Walls )
Planning, Design & Construction

4 of 5
Hale 12-Dec 22, 2022.png
December 23, 2022- (Hale 12 Foot Plan-Tie Rebar)
Planning, Design & Construction

5 of 5
Hale 11-Dec 22, 2022.png
December 23, 2022- (Hale 11-Foot Plan)
Planning, Design & Construction
1
of
5
Timeline and Updates of the Project
Completion Date
Hale 13- Mid 2024
Hale 12 - Fall 2024
Hale 11 - Early 2025
Recent Update
December 23, 2022-January 3, 2023
- Waterline for Hale 12 and 11 were installed.
- Insulated Concrete Form (ICF) walls began for Hale 13 Area A Sequence 2
- Slab-on-grade has also been poured for Hale 13 Sequence 2 on December 21.
- Storm drain install in courtyard completed and waterproof Surf/Bike completed for Hale 11 and Hale 12.
- Started rebar at Sequence 3 and 2 for Hale 12.
- Concrete pour on sequence 4 and 6 Hale 12 footings.
1 of 19
New Hale Update Photo 1.PNG
November 1, 2022-Asphalt Paving First Lift North Roadway Completed
Planning, Design & Construction Department
2 of 19
New Hale Update Photo 2.PNG
November 1, 2022 - Asphalt Paving First Lift North Roadway Completed
Planning, Design & Construction Department
3 of 19
Hale 12.PNG
November 1, 2022 - Asphalt Paving First Lift North Roadway Completed
November 1, 2022 - Asphalt Paving First Lift North Roadway Completed
4 of 19
Hale 11 update.PNG
November 1, 2022 - Asphalt Paving First Lift North Roadway Completed
November 1, 2022 - Asphalt Paving First Lift North Roadway Completed
5 of 19
Hale 11-Footings 1.PNG
November 1, 2022 - Asphalt Paving First Lift North Roadway Completed
6 of 19
New Hale Update Photo 4.PNG
November 1, 2022 - Asphalt Paving First Lift North Roadway Completed
7 of 19
Mock up room.PNG
Planning, Design & Construction Department

8 of 19
Project Overview Hale 11-13 (Nov 25, 2022).png
November 25, 2022- Project Overview
Planning, Design & Construction

9 of 19
Hale 13-Nov 25, 2022.png
November 25, 2022- Hale 13 Construction Update
Planning, Design & Construction Department

10 of 19
Hale 13-Sequence 1-Nov 25, 2022.png
November 25, 2022-Hale 13 Sequence 1-Project Overview
Planning, Design & Construction Department

11 of 19
Hale 13 Sequence- Nov 25, 2022.png
November 25, 2022-Hale 13 Sequence-Project Overview
Planning, Design & Construction

12 of 19
Hale 12-Nov 25, 2022.png
November 25, 2022- Hale 12 Project Overview
Planning, Design & Construction Department

13 of 19
Hale 11-Nov 25, 2022.png
November 25, 2022-Hale 13 Project Overview
Planning, Design & Construction

14 of 19
Unit-Mock-Up-Nov 25, 2022.png
November 25, 2022- Unit Mock-Up Room-Project Overview
Planning, Design & Construction Department

15 of 19
Hale 11-13- Dec 22 2022.png
December 22, 2022- (Hale 11, 12, and 13 Construction Site Project Overview)
Planning, Design & Construction

16 of 19
Hale 13-Dec 22, 2022.png
December 23, 2022- (Hale 13 Area A Sequences 1-3) Project Overview
Planning, Design & Construction

17 of 19
Hale 13-Dec 12, 2022.png
December 22, 2022-Hale 13 (Insulated Concrete Form Walls )
Planning, Design & Construction

18 of 19
Hale 12-Dec 22, 2022.png
December 23, 2022- (Hale 12 Foot Plan-Tie Rebar)
Planning, Design & Construction

19 of 19
Hale 11-Dec 22, 2022.png
December 23, 2022- (Hale 11-Foot Plan)
Planning, Design & Construction
1
of
19
1 of 19
New Hale Update Photo 1.PNG
November 1, 2022-Asphalt Paving First Lift North Roadway Completed
Planning, Design & Construction Department
2 of 19
New Hale Update Photo 2.PNG
November 1, 2022 - Asphalt Paving First Lift North Roadway Completed
Planning, Design & Construction Department
3 of 19
Hale 12.PNG
November 1, 2022 - Asphalt Paving First Lift North Roadway Completed
November 1, 2022 - Asphalt Paving First Lift North Roadway Completed
4 of 19
Hale 11 update.PNG
November 1, 2022 - Asphalt Paving First Lift North Roadway Completed
November 1, 2022 - Asphalt Paving First Lift North Roadway Completed
5 of 19
Hale 11-Footings 1.PNG
November 1, 2022 - Asphalt Paving First Lift North Roadway Completed
6 of 19
New Hale Update Photo 4.PNG
November 1, 2022 - Asphalt Paving First Lift North Roadway Completed
7 of 19
Mock up room.PNG
Planning, Design & Construction Department

8 of 19
Project Overview Hale 11-13 (Nov 25, 2022).png
November 25, 2022- Project Overview
Planning, Design & Construction

9 of 19
Hale 13-Nov 25, 2022.png
November 25, 2022- Hale 13 Construction Update
Planning, Design & Construction Department

10 of 19
Hale 13-Sequence 1-Nov 25, 2022.png
November 25, 2022-Hale 13 Sequence 1-Project Overview
Planning, Design & Construction Department

11 of 19
Hale 13 Sequence- Nov 25, 2022.png
November 25, 2022-Hale 13 Sequence-Project Overview
Planning, Design & Construction

12 of 19
Hale 12-Nov 25, 2022.png
November 25, 2022- Hale 12 Project Overview
Planning, Design & Construction Department

13 of 19
Hale 11-Nov 25, 2022.png
November 25, 2022-Hale 13 Project Overview
Planning, Design & Construction

14 of 19
Unit-Mock-Up-Nov 25, 2022.png
November 25, 2022- Unit Mock-Up Room-Project Overview
Planning, Design & Construction Department

15 of 19
Hale 11-13- Dec 22 2022.png
December 22, 2022- (Hale 11, 12, and 13 Construction Site Project Overview)
Planning, Design & Construction

16 of 19
Hale 13-Dec 22, 2022.png
December 23, 2022- (Hale 13 Area A Sequences 1-3) Project Overview
Planning, Design & Construction

17 of 19
Hale 13-Dec 12, 2022.png
December 22, 2022-Hale 13 (Insulated Concrete Form Walls )
Planning, Design & Construction

18 of 19
Hale 12-Dec 22, 2022.png
December 23, 2022- (Hale 12 Foot Plan-Tie Rebar)
Planning, Design & Construction

19 of 19
Hale 11-Dec 22, 2022.png
December 23, 2022- (Hale 11-Foot Plan)
Planning, Design & Construction
1
of
19
Construction Gallery
1 of 32
03.02 Ground
2 of 32
03.02 First Hale
3 of 32
03.02 Hale Groundwork
4 of 32
03-10 South View Sites
5 of 32
03-10 Leveling and Pouring dirt
6 of 32
03-10 East View Ground Prep
7 of 32
03.10 Aerial of Hales Old and New
8 of 32
03.15 Aerial of Laie
9 of 32
03.15 Aerial of the Hales
10 of 32
03.15 Building Pad
11 of 32
3.29 Aerial Building Pads
12 of 32
3.29 Aerial of Laie
13 of 32
3.29 Aerial looking towards the Temple
14 of 32
New Hale Update Photo 1.PNG
November 1, 2022-Asphalt Paving First Lift North Roadway Completed
Planning, Design & Construction Department
15 of 32
New Hale Update Photo 2.PNG
November 1, 2022 - Asphalt Paving First Lift North Roadway Completed
Planning, Design & Construction Department
16 of 32
Hale 12.PNG
November 1, 2022 - Asphalt Paving First Lift North Roadway Completed
November 1, 2022 - Asphalt Paving First Lift North Roadway Completed
17 of 32
Hale 11 update.PNG
November 1, 2022 - Asphalt Paving First Lift North Roadway Completed
November 1, 2022 - Asphalt Paving First Lift North Roadway Completed
18 of 32
Hale 11-Footings 1.PNG
November 1, 2022 - Asphalt Paving First Lift North Roadway Completed
19 of 32
New Hale Update Photo 4.PNG
November 1, 2022 - Asphalt Paving First Lift North Roadway Completed
20 of 32
Mock up room.PNG
Planning, Design & Construction Department

21 of 32
Project Overview Hale 11-13 (Nov 25, 2022).png
November 25, 2022- Project Overview
Planning, Design & Construction

22 of 32
Hale 13-Sequence 1-Nov 25, 2022.png
November 25, 2022-Hale 13 Sequence 1-Project Overview
Planning, Design & Construction Department

23 of 32
Hale 13-Nov 25, 2022.png
November 25, 2022- Hale 13 Construction Update
Planning, Design & Construction Department

24 of 32
Hale 13 Sequence- Nov 25, 2022.png
November 25, 2022-Hale 13 Sequence-Project Overview
Planning, Design & Construction

25 of 32
Hale 12-Nov 25, 2022.png
November 25, 2022- Hale 12 Project Overview
Planning, Design & Construction Department

26 of 32
Hale 11-Nov 25, 2022.png
November 25, 2022-Hale 13 Project Overview
Planning, Design & Construction

27 of 32
Unit-Mock-Up-Nov 25, 2022.png
November 25, 2022- Unit Mock-Up Room-Project Overview
Planning, Design & Construction Department

28 of 32
Hale 11-13- Dec 22 2022.png
December 22, 2022- (Hale 11, 12, and 13 Construction Site Project Overview)
Planning, Design & Construction

29 of 32
Hale 13-Dec 22, 2022.png
December 23, 2022- (Hale 13 Area A Sequences 1-3) Project Overview
Planning, Design & Construction

30 of 32
Hale 13-Dec 12, 2022.png
December 22, 2022-Hale 13 (Insulated Concrete Form Walls )
Planning, Design & Construction

31 of 32
Hale 12-Dec 22, 2022.png
December 23, 2022- (Hale 12 Foot Plan-Tie Rebar)
Planning, Design & Construction

32 of 32
Hale 11-Dec 22, 2022.png
December 23, 2022- (Hale 11-Foot Plan)
Planning, Design & Construction
1
of
32
1 of 32
03.02 Ground
2 of 32
03.02 First Hale
3 of 32
03.02 Hale Groundwork
4 of 32
03-10 South View Sites
5 of 32
03-10 Leveling and Pouring dirt
6 of 32
03-10 East View Ground Prep
7 of 32
03.10 Aerial of Hales Old and New
8 of 32
03.15 Aerial of Laie
9 of 32
03.15 Aerial of the Hales
10 of 32
03.15 Building Pad
11 of 32
3.29 Aerial Building Pads
12 of 32
3.29 Aerial of Laie
13 of 32
3.29 Aerial looking towards the Temple
14 of 32
New Hale Update Photo 1.PNG
November 1, 2022-Asphalt Paving First Lift North Roadway Completed
Planning, Design & Construction Department
15 of 32
New Hale Update Photo 2.PNG
November 1, 2022 - Asphalt Paving First Lift North Roadway Completed
Planning, Design & Construction Department
16 of 32
Hale 12.PNG
November 1, 2022 - Asphalt Paving First Lift North Roadway Completed
November 1, 2022 - Asphalt Paving First Lift North Roadway Completed
17 of 32
Hale 11 update.PNG
November 1, 2022 - Asphalt Paving First Lift North Roadway Completed
November 1, 2022 - Asphalt Paving First Lift North Roadway Completed
18 of 32
Hale 11-Footings 1.PNG
November 1, 2022 - Asphalt Paving First Lift North Roadway Completed
19 of 32
New Hale Update Photo 4.PNG
November 1, 2022 - Asphalt Paving First Lift North Roadway Completed
20 of 32
Mock up room.PNG
Planning, Design & Construction Department

21 of 32
Project Overview Hale 11-13 (Nov 25, 2022).png
November 25, 2022- Project Overview
Planning, Design & Construction

22 of 32
Hale 13-Sequence 1-Nov 25, 2022.png
November 25, 2022-Hale 13 Sequence 1-Project Overview
Planning, Design & Construction Department

23 of 32
Hale 13-Nov 25, 2022.png
November 25, 2022- Hale 13 Construction Update
Planning, Design & Construction Department

24 of 32
Hale 13 Sequence- Nov 25, 2022.png
November 25, 2022-Hale 13 Sequence-Project Overview
Planning, Design & Construction

25 of 32
Hale 12-Nov 25, 2022.png
November 25, 2022- Hale 12 Project Overview
Planning, Design & Construction Department

26 of 32
Hale 11-Nov 25, 2022.png
November 25, 2022-Hale 13 Project Overview
Planning, Design & Construction

27 of 32
Unit-Mock-Up-Nov 25, 2022.png
November 25, 2022- Unit Mock-Up Room-Project Overview
Planning, Design & Construction Department

28 of 32
Hale 11-13- Dec 22 2022.png
December 22, 2022- (Hale 11, 12, and 13 Construction Site Project Overview)
Planning, Design & Construction

29 of 32
Hale 13-Dec 22, 2022.png
December 23, 2022- (Hale 13 Area A Sequences 1-3) Project Overview
Planning, Design & Construction

30 of 32
Hale 13-Dec 12, 2022.png
December 22, 2022-Hale 13 (Insulated Concrete Form Walls )
Planning, Design & Construction

31 of 32
Hale 12-Dec 22, 2022.png
December 23, 2022- (Hale 12 Foot Plan-Tie Rebar)
Planning, Design & Construction

32 of 32
Hale 11-Dec 22, 2022.png
December 23, 2022- (Hale 11-Foot Plan)
Planning, Design & Construction
1
of
32