Naniloa Loop Improvements


Project Summary
Renovation
Completion Date: October 2021
This project improves the streetscape of Naniloa Loop on the BYUH side as well as extend the low white fence that fronts the University. The improvements also upgrades the pedestrian frontage and provide a bike lane to improve connectivity.
The goal is to provide a clear physical and aesthetic connection between BYUH and the Laie Hawaii Temple that will represent the connection these two institutions have in purpose and mission.
Construction Gallery
1 of 17
Naniloa Loop-Overall Site
June 2021 - The Fencing Has Been Installed in Preparation for the Construction
2 of 17
The New Fencing #1
June 2021 - The Fencing Has Been Installed in Preparation for the Construction
3 of 17
The New Fencing #2
June 2021 - The Fencing Has Been Installed in Preparation for the Construction

4 of 17
Ground Preparation.jpg
June 28, 2021 - Ground Preparation

5 of 17
Leveling the Ground.jpg
July 5, 2021 - Leveling the Ground

6 of 17
Ground is Ready.jpg
July 12, 2021 - Ground is Ready

7 of 17
Rebar Placement.jpg
July 19, 2021 - Rebar Placement

8 of 17
Concrete Pour.jpg
July 12, 2021 - Concrete Pour
9 of 17
The Sidewalk has been Installed
July 28, 2021 - The Sidewalk has been Installed

10 of 17
Concrete Pour Update.jpg
August 2, 2021 - Concrete Pour Update

11 of 17
Concrete Work Progress.jpg
August 9, 2021 - Concrete Work Progress

12 of 17
Sidewalk Progress.jpg
August 16, 2021 - Sidewalk Progress

13 of 17
Sidewalk Progress #2.jpg
September 6, 2021 - Sidewalk Progress #2

14 of 17
Concrete Pour Update #2.jpg
September 13, 2021 - Concrete Pour Update #2

15 of 17
Last Part of the Sidewalk Construction.jpg
October 11, 2021 - Last Part of the Sidewalk Construction

16 of 17
Concrete Pour Completed.jpg
October 18, 2021 - Concrete Pour Completed

17 of 17
Completed Naniloa Loop Improvements.jpg
Completed Naniloa Loop Improvement
1
of
17
1 of 17
Naniloa Loop-Overall Site
June 2021 - The Fencing Has Been Installed in Preparation for the Construction
2 of 17
The New Fencing #1
June 2021 - The Fencing Has Been Installed in Preparation for the Construction
3 of 17
The New Fencing #2
June 2021 - The Fencing Has Been Installed in Preparation for the Construction

4 of 17
Ground Preparation.jpg
June 28, 2021 - Ground Preparation

5 of 17
Leveling the Ground.jpg
July 5, 2021 - Leveling the Ground

6 of 17
Ground is Ready.jpg
July 12, 2021 - Ground is Ready

7 of 17
Rebar Placement.jpg
July 19, 2021 - Rebar Placement

8 of 17
Concrete Pour.jpg
July 12, 2021 - Concrete Pour
9 of 17
The Sidewalk has been Installed
July 28, 2021 - The Sidewalk has been Installed

10 of 17
Concrete Pour Update.jpg
August 2, 2021 - Concrete Pour Update

11 of 17
Concrete Work Progress.jpg
August 9, 2021 - Concrete Work Progress

12 of 17
Sidewalk Progress.jpg
August 16, 2021 - Sidewalk Progress

13 of 17
Sidewalk Progress #2.jpg
September 6, 2021 - Sidewalk Progress #2

14 of 17
Concrete Pour Update #2.jpg
September 13, 2021 - Concrete Pour Update #2

15 of 17
Last Part of the Sidewalk Construction.jpg
October 11, 2021 - Last Part of the Sidewalk Construction

16 of 17
Concrete Pour Completed.jpg
October 18, 2021 - Concrete Pour Completed

17 of 17
Completed Naniloa Loop Improvements.jpg
Completed Naniloa Loop Improvement
1
of
17