Fitness Studio
Project Summary
Renovation
Completion Date: October 2020
The existing Weight Room is too small to serve the current campus community. In an attempt to provide additional fitness areas, the racquetball courts is transformed into a new workout space. Two of the three courts is remodeled to receive new fitness equipment and the third court is transformed into a fitness classroom. Besides these internal changes, additional exterior space is created to meet student needs. The building receives necessary structural upgrades and new air conditioning.
Construction Gallery

1 of 30
Construction Markings #2
March 20, 2020 - The Construction Markings have been Put
BYUH Planning, Design, & Construction

2 of 30
Construction Markings
March 20, 2020 - The Construction Markings Have Been Put
BYUH Planning, Design, & Construction

3 of 30
Screen Shot 2020-05-07 at 3.15.58 PM.png
April 2020 - Rebar Placement for the Walkway Extension
BYUH Planning, Design, & Construction

4 of 30
Screen Shot 2020-05-07 at 3.23.41 PM.png
April 2020 - Ground Preparation
BYUH Planning, Design, & Construction

5 of 30
Screen Shot 2020-05-07 at 3.15.41 PM.png
April 2020 - Rebar Placement Preparation
BYUH Planning, Design, & Construction

6 of 30
Screen Shot 2020-06-02 at 9.02.04 AM.png
May 25, 2020 - Preparation for Rebar Placement
BYUH Planning, Design, & Construction

7 of 30
Screen Shot 2020-06-02 at 9.02.14 AM.png
May 25, 2020 - Preparation for Rebar Placement #2
BYUH Planning, Design, & Construction

8 of 30
Screen Shot 2020-06-02 at 9.02.25 AM.png
May 25, 2020 - Rebar Placement
BYUH Planning, Design, & Construction

9 of 30
Concrete Forming
June 8, 2020 - Concrete Forming
BYUH Planning, Design, & Construction

10 of 30
Trench Drain Excavation
June 8, 2020 - Trench Drain Excavation
BYUH Planning, Design, & Construction

11 of 30
Interior Electrical Demolition
June 8, 2020 - Interior Electrical Demolition
BYUH Planning, Design, & Construction
12 of 30
Concrete Walk Way Extension
June 25, 2020 - Concrete Walkway Extension
BYUH Planning, Design, & Construction
13 of 30
The Concrete Walkway Extension
June 25, 2020 - The Concrete Walkway Extension
BYUH Planning, Design, & Construction
14 of 30
Image Before Rebar Placement
June 25, 2020 - Image Before Rebar Placement
BYUH Planning, Design, & Construction
15 of 30
Forms ready for pouring slabs at Racquetball Court area.
June 25, 2020 - Metal and Wooden Forms for Pouring Slabs
BYUH Planning, Design, & Construction

16 of 30
Concrete Placement #1
June 29, 2020 - Concrete Placement #1
BYUH Planning, Design, & Construction

17 of 30
Concrete Placement #2
June 29, 2020 - Concrete Placement #2
BYUH Planning, Design, & Construction

18 of 30
Concrete and Trench Drain
July 20, 2020 - Concrete and Trench Drain
BYUH Planning, Design, & Construction

19 of 30
Concrete Work is Complete
July 20, 2020 - Concrete Work is Completed
BYUH Planning, Design, & Construction

20 of 30
Soffit Demolition
July 20, 2020 - Soffit Demolition
BYUH Planning, Design, & Construction

21 of 30
July 20, 2020 Update.png
July 20, 2020 - Adding Vestibule Framing to Fitness Studio
BYUH Planning, Design, & Construction

22 of 30
Lighting and Fans Installed
September 14, 2020 - Lighting and Fans Installed
BYUH Planning, Design, & Construction

23 of 30
Mirrors in Progress
September 14, 2020 - Mirrors in Progress
BYUH Planning, Design, & Construction

24 of 30
Storefront Install
September 28, 2020 - Storefront Install
BYUH Planning, Design, & Construction

25 of 30
A Glass Door from the Inside and the Outside
September 28, 2020 - A Glass Door from the Inside and the Outside
BYUH Planning, Design, & Construction

26 of 30
Fitness Studio Interior Work is Complete
October 19, 2020 - Interior Work is Complete
BYUH Planning, Design, & Construction

27 of 30
Fitness Studio is Complete
October 19, 2020 - Fitness Studio is Complete
BYUH Planning, Design, & Construction
28 of 30
Fitness Equipment #1
October 30, 2020 - Fitness Equipment #1
BYUH Planning, Design, & Construction
29 of 30
Fitness Equipment #2
October 30, 2020 - Fitness Equipment #2
BYUH Planning, Design, & Construction

30 of 30
Fitness Studio Completed
October 2020 - Outside Design of Fitness Studio is Completed
BYUH Planning, Design, & Construction